1. Owner
2. End user
3. architect
4. electrical engineer
5. mechanical engineer
6. commissioning authority
7. controls contractor
8. mechanical contractor
9. electrical contractor
10. sheet metal contractor
11. TAB agency
12. General or construction manager
13. owners O&M staff - Answers Identify typical team member of the Cx Team.
1. commissioning starts at the inception of a building project during the pre-design phase, and continues
through the post-acceptance phase.
2. provides an opportunity to cultivate a quality management focus among all design and construction
team members as they become involved with the project - Answers Comprehensive Commissioning
Chapter 5 - Answers Which Chapter of the ACG guideline identifies detailed methodology for
Comprehensive HVAC Commissioning?
Pre-design
Design
Construction
Acceptance
Post Acceptance - Answers What are the Comprehensive Commissioning phases?
1. Commissioning established as integral part of project
, 2. The owner selects the commissioning authority
3. Develop the scope of commissioning
4. Commissioning authority reviews design intent document - Answers Comprehensive Commissioning:
Pre-design phase
1. Review design to ensure it accommodates commissioning
2. Write commissioning specifications defining contractor
responsibilities
3. Commissioning authority writes the commissioning plan
4. Establish the project schedule - Answers Comprehensive Commissioning Design phase
1. Commissioning authority reviews contractor submittals
2. Commissioning authority updates commissioning plan
3. Commissioning process is coordinated—through project
schedule, commissioning plan and commissioning plan
and commissioning meetings
4. Carry out and document system verification checks
5. Carry out the document equipment and system start-ups
6. TAB agency completes and documents TAB work - Answers Comprehensive Commissioning
Construction phase
1. Carry out FPTs on all HVAC systems
2. Train the O&M staff for effective, ongoing operations and maintenance of all systems
3. Provide full documentation - Answers Comprehensive Commissioning Acceptance phase
1. Correct any deficiencies, carry out required re-testing
2. Carry out any required "off-season" tests
3. Update documentation as required - Answers Comprehensive Commissioning Post-Acceptance phase
- Answers Identify the Comprehensive HVAC commissioning organizational structure for Plan & Spec
1. Authority leads the commissioning process, and works