Verification of performance of inspection and testing programs shall do which of the following
to - CORRECT ANSWER - Verify that the installed system meets the operation
requirements of the version of code when the system was installed, verify the correct operation
of the system.
Which of the following shall be done when conducting tests in lead-acid type batteries -
CORRECT ANSWER - Annually conduct a discharge test with the charger disconnected
while conducting a load test with full alarm load or an artificial load,
Area of refuge two-way communication systems are required to be tested in which of the
following three ways - CORRECT ANSWER - Verify Receipt of visual and audible signal
at the transmitting and receiving unit, respectively
How often shall secondary power supply be tested? - CORRECT ANSWER - Annually
How often are video image smoke and fire detectors required to be inspected? - CORRECT
ANSWER - Annually
Which two of the following are true regarding acceptable test plans? - CORRECT
ANSWER - Shall be documented with the testing records, shall be written to clearly
establish the scope of the testing for the fire alarm or signaling system.
How often shall fire optic cable connections be inspected? - CORRECT ANSWER -
Annually
How many years after the initial installation shall all fixed temperature non restorable line type
detectors be replaced or have 2 per 100 laboratory tested? - CORRECT ANSWER - 20