Project Management Exam Review Questions and
Correct Answers/ Latest Update / Already
Graded
Which of the following provides certification as a Project Management
Professional?
Select one:
a.
PMI
b.
PMC
c.
PMP
d.
PMS
Ans: CorrectRationale:
Feedback: PMI or the Project Management Institute provides certification as a
Project Management Professional (PMP). A Project Management Professional (PMP)
is someone who has documented sufficient project experience and education,
agreed to follow the PMI code of professional conduct, and demonstrated
knowledge of project management by passing a comprehensive examination.
Which of the following is true of program managers?
Select one:
a.
They recognize that managing a program is simpler than managing a project.
, 2 | Page
b.
They report to project managers who represent the next level in the hierarchy.
c.
They are responsible solely for the delivery of project results.
d.
They provide leadership and direction for project managers heading the projects
within a program.
Ans: D.They provide leadership and direction for project managers heading the
projects within a program.
Which of the following statements is true of project management?
Select one:
a.
It has specific tools which work universally across all kinds of projects.
b.
It does not guarantee successes for all projects.
c.
Its framework consists solely of project management knowledge areas.
d.
It is a simple discipline with a limited scope.
Ans: B. It does not guarantee successes for all projects.
Which of the following is a difference between projects and operations?
Select one:
a.
, 3 | Page
Projects are temporary endeavors whereas an organization's operations are
ongoing in nature.
b.
Operations have well-defined objectives whereas projects do not need to have a
unique purpose.
c.
Projects are undertaken to sustain an organization's business whereas operations
are not.
d.
Operations are undertaken to create unique products, services, or results whereas
projects are not.
Ans: Projects are temporary endeavors whereas an organization's operations are
ongoing in nature.
A difference between strategic and tactical goals is that:
Select one:
a.
strategic goals are more specific than tactical goals.
b.
tactical goals are more important for a project than strategic goals.
c.
tactical goals encompass broader dimensions than strategic goals.
d.
strategic goals are long-term in nature whereas tactical goals are short-term.
, 4 | Page
Ans: d.
strategic goals are long-term in nature whereas tactical goals are short-term.
In which of the following areas of management is payback analysis most likely to
be used?
Select one:
a.
Quality
b.
Human resource
c.
Cost
d.
Communication
Ans: C. Cost
Project _____ management involves defining and managing all the work required
to complete the project successfully.
Select one:
a.
human resource
b.
time
c.
scope