A vendor who was not selected for a contract decides to
protest the decision. How long after filing a written notice of
intent to protest does a vendor have to file the formal written
protest? - Correct Answer ✅ 10 Days
Seven Stages of Public Procurement - Correct Answer ✅
Identification
Pre-Solicitation
Solicitation Prep
Solicitation
Response Evaluation
Contract Award
Contract Management
When the total cost of the needed commodities or
contractual services exceeds $35,000 the solicitation must be
- Correct Answer ✅ competitive
, FCCM Training Knowledge Checks (Latest
Update 2025)
Which payment method is used when a project is divided into
intervals, and payment is distributed at those intervals -
Correct Answer ✅ Fixed Price
Which method of competitive solicitation would someone
want to use when the focus is on price plus quality - Correct
Answer ✅ Request for proposal
Which documents are generally included in a competitive
solicitation - Correct Answer ✅ Scope of Work
Which purchasing category is required to have at least three
people assigned to an evaluation or negotiation team? -
Correct Answer ✅ Category 4 ($195,00)
What type of solicitation must be publicly posted on the
Vendor Bid System? - Correct Answer ✅ Competitive
If a vendor has a question regarding a solicitation, who must
they contact? - Correct Answer ✅ Procurement officer