Circuit testers assess if ______ electricity is present - answer AC.
In a PM audit, a large number of uncompleted PM work orders would most likely
have a negative influence on the results. - ANSWER Critical Path
What is the purpose of Total Productive Maintenance (TPM)? - ANSWER: Zero
failures and faults.
A chain should be changed when it reaches a length that is _______ longer than the
original. - ANSWER 3 percent
Before shutting down a machine for preventive maintenance, the maintenance
specialist must remove all of the trash and sediment from the machine.
Where would a worker obtain information regarding the use of all lubricants and
safety precautions—ANSWER SDS file
When lubricating a bearing, the worst mistake is to get dirt in the bearing.
The most evident evidence that V-belt pulleys are worn beyond usefulness is when
the ANSWER belt touches the bottom of the groove.
Which of the following is an essential planned maintenance activity? ANSWER:
Lubricate equipment.
Preventive maintenance programs would often include ANSWER frequency.
It is vital to have a/an ________ for the closure of PM work orders. ANSWER
completion date
, Frequently, the employee finishing out the PM work order ensures that - ANSWER
preventive maintenance was accomplished.
Which of the following bolts has a value of 5? - Answer the screw with three lines.
Scheduled repair of minor parts that wear quickly is a crucial aspect of __________
maintenance. - The answer is preventive.
Which of the following would be considered an unscheduled downtime
maintenance activity? - ANSWER Reactive Maintenance
All documentation for preventative maintenance should be retained in a specified,
safe, and secure area.
Making sure that a motor shaft is level - ANSWER lowers the amount of required
shims
When testing for out-of-round, any movement of the dial indicates that the -
ANSWER shaft could be out-of-round.
Follow-up work created after considering PM - ANSWER predictive
Daily maintenance requires keeping daily records since repeating events can be
studied to troubleshoot problems.
A machine is expected to have downtime throughout multiple shifts. What is the
proper way to communicate between shifts for lockout/tagout procedures? -
ANSWER Send a company-wide email; maintenance personnel should check for
energy and change locks.
Circuit testers assess if ______ electricity is present - answer AC.
In a PM audit, a large number of uncompleted PM work orders would most likely
have a negative influence on the results. - ANSWER Critical Path
What is the purpose of Total Productive Maintenance (TPM)? - ANSWER: Zero
failures and faults.
A chain should be changed when it reaches a length that is _______ longer than the
original. - ANSWER 3 percent
Before shutting down a machine for preventive maintenance, the maintenance
specialist must remove all of the trash and sediment from the machine.
Where would a worker obtain information regarding the use of all lubricants and
safety precautions—ANSWER SDS file
When lubricating a bearing, the worst mistake is to get dirt in the bearing.
The most evident evidence that V-belt pulleys are worn beyond usefulness is when
the ANSWER belt touches the bottom of the groove.
Which of the following is an essential planned maintenance activity? ANSWER:
Lubricate equipment.
Preventive maintenance programs would often include ANSWER frequency.
It is vital to have a/an ________ for the closure of PM work orders. ANSWER
completion date
, Frequently, the employee finishing out the PM work order ensures that - ANSWER
preventive maintenance was accomplished.
Which of the following bolts has a value of 5? - Answer the screw with three lines.
Scheduled repair of minor parts that wear quickly is a crucial aspect of __________
maintenance. - The answer is preventive.
Which of the following would be considered an unscheduled downtime
maintenance activity? - ANSWER Reactive Maintenance
All documentation for preventative maintenance should be retained in a specified,
safe, and secure area.
Making sure that a motor shaft is level - ANSWER lowers the amount of required
shims
When testing for out-of-round, any movement of the dial indicates that the -
ANSWER shaft could be out-of-round.
Follow-up work created after considering PM - ANSWER predictive
Daily maintenance requires keeping daily records since repeating events can be
studied to troubleshoot problems.
A machine is expected to have downtime throughout multiple shifts. What is the
proper way to communicate between shifts for lockout/tagout procedures? -
ANSWER Send a company-wide email; maintenance personnel should check for
energy and change locks.