Question 1
A senior programmer ignores the organization’s coding standards, performs only
basic unit testing, and deploys code directly into production. The program
subsequently fails in the live environment and requires emergency maintenance. What
is the most significant long-term consequence of the programmer’s actions?
A. The project’s velocity will automatically increase
B. The team will eliminate unnecessary documentation
C. The programmer has increased the project’s technical debt
D. The production failure proves that unit testing is unnecessary
Correct Answer: C. The programmer has increased the project’s technical debt
Rationale: Technical debt results when a team takes shortcuts that create additional
corrective work in the future. Ignoring coding standards, performing insufficient
testing, and deploying without proper controls increase maintenance costs and system
risk. Velocity does not necessarily increase, and the incident does not justify
eliminating documentation or testing. Instead, it demonstrates why disciplined
engineering practices are essential.
Question 2
During a sprint, a stakeholder asks the Scrum Team to add a high-priority feature and
remove two existing sprint backlog items. Which response is most consistent with
Scrum rules?
A. The Product Owner may directly replace the sprint backlog items
B. The Scrum Master should add the feature because it has high business value C.
The Developers may renegotiate scope with the Product Owner without
endangering the Sprint Goal
D. The customer may change sprint scope whenever market conditions change
Correct Answer: C. The Developers may renegotiate scope with the Product
Owner without endangering the Sprint Goal
Rationale: Sprint scope is not casually changed by stakeholders, the Product Owner,
or the Scrum Master. However, the Developers and Product Owner may clarify or
renegotiate work as more is learned, provided the Sprint Goal remains achievable.
Directly adding or removing work without team collaboration undermines
commitment, focus, and the stability provided by the sprint timebox.
,2026/2027
Question 3
Two development team members repeatedly disagree about architectural decisions.
Their manager avoids addressing the conflict, and communication between them
gradually deteriorates. Which outcome is most likely?
A. Increased creativity without any negative consequences
B. Lower productivity and damaged working relationships
C. Greater technical specialization across the team
D. Faster decision-making because fewer discussions occur
Correct Answer: B. Lower productivity and damaged working relationships
Rationale: Poorly managed conflict commonly reduces trust, collaboration, and
productivity. Although constructive conflict can generate creativity, unresolved
interpersonal tension often causes delays, rework, information withholding, and
deteriorating relationships. Technical specialization does not resolve the underlying
problem, and avoiding discussion may produce faster superficial decisions but usually
results in weaker outcomes and greater long-term disruption.
Question 4
A product team wants to apply the Agile principle of customer satisfaction throughout
a twelve-month project. Which strategy best supports this objective?
A. Deliver all functionality in a single release at project completion
B. Continuously deliver valuable, usable software increments
C. Minimize customer interaction until system testing is complete
D. Finalize every requirement before beginning development
Correct Answer: B. Continuously deliver valuable, usable software increments
Rationale: Agile promotes early and continuous delivery of valuable software as the
primary means of satisfying customers. Frequent delivery allows customers to
evaluate real outcomes, provide feedback, and redirect priorities. A single final
release delays value and learning. Limited customer interaction and complete upfront
requirements reduce adaptability and increase the risk of delivering an unsuitable
product.
Question 5
A client reports that several completed work units do not satisfy the agreed quality
expectations. As the project lead, what should you do first?
A. Replace the team members responsible for the work
B. Ask the client to revise the acceptance criteria
, 2026/2027
C. Meet with the team to understand the situation and develop a strategy for meeting
the acceptance criteria
D. Extend the iteration so the team can correct every deficiency
Correct Answer: C. Meet with the team to understand the situation and develop
a strategy for meeting the acceptance criteria
Rationale: The lead should first investigate the underlying causes collaboratively and
determine why the delivered work failed to meet acceptance criteria. This supports
transparency, learning, and corrective action. Replacing team members is premature,
while asking the client to weaken criteria avoids accountability. Extending the
iteration violates timeboxing and may conceal problems rather than resolving them
systematically.
Question 6
A Product Owner categorizes requirements as Must Have, Should Have, Could Have,
and Will Not Have at this time. What is the principal purpose of this activity?
A. Estimating the monetary cost of each requirement
B. Assigning requirements to individual developers
C. Determining the relative priority of requirements
D. Calculating the team’s sprint velocity
Correct Answer: C. Determining the relative priority of requirements
Rationale: The MoSCoW technique helps stakeholders and product leaders
distinguish essential requirements from desirable or deferrable ones. It supports
prioritization and informed scope decisions. It does not directly estimate cost, assign
work, or calculate velocity. Those activities require separate estimation, planning, and
team-capacity processes.
Question 7
A project team is reviewing common sources of conflict in Agile environments.
Which factor is least likely to be considered a primary Agile-specific source of
conflict?
A. Differences in priorities
B. Competition for limited resources
C. Conflicting technical approaches
D. Stringent deadlines established as an isolated factor
Correct Answer: D. Stringent deadlines established as an isolated factor