●● 2. Raceways are taken off per _____. Fittings required to make turns
and extensions are taking off per _____.
Answer: Linear foot, each
●● 3. All wires and conductors are taken off per _____.
Answer: Linear foot
●● 4. All fittings, devices and boxes are taken off per _____.
Answer: Each Item
●● 5. Permits and fees for tie-ins may be listed at lump sum and are
taken off per _____.
Answer: Occurrence,Project, and Contract
●● 6. Control stations are taken off by _______.
Answer: Individual Unit and Each Item.
●● 7. Panelboards are taken off individually according to ______.
,Answer: Type, Size, and Voltage
●● 8. Starters, safety switches and fuses are taken off per _______.
Answer: Each Item
●● 9. _______ should be kept separate from general light fixtures.
Answer: Exit Lighting
●● 10. Interior and exterior lighting should be taken off and listed
_______.
Answer: Separately
●● 11. Lamps for light fixtures are _______.
Answer: Taken off per each Item
●● 12. Light fixtures should be listed in the takeoff according to
_______.
Answer: Color
●● 13. Working electrical drawings numbered sequentially, prefaced by
the letter "E", include _______.
Answer: Telecommunications and security systems only
,●● 14. The _______ shows power requirements of the structure.
Answer: Power plan
●● 15. The _______ aids the electrical contractor sizing the panel.
Answer: Panel Schedule
●● 16. The _______ plan is supplemented by the fixture schedule.
Answer: Lighting
●● 17. The fixture schedule lists lamp _______.
Answer: Wattage
●● 18. Electrical specifications provide _______.
Answer: The grade of materials to be used, Materials installation
specifics, and how materials will be used in the finished system
●● 19. _______ must be maintained by the electrical contractor for all
installed work.
Answer: As-built drawings
●● 20. No conductors are smaller than No. _______ wire.
Answer: 12
, ●● 21. _______ Shall be installed in service entrances and panel feeders.
Answer: Rigid conduit
●● 22. The electrical contractor is responsible for providing and
installing _______ for a complete telephone system.
Answer: Outlet boxes, pull boxes, and empty raceways
●● 23. Interpretation of construction drawings and specifications may
conflict when _______.
Answer: Standard specifications are used with specific working plans,
previously prepared plans are changed and referenced in the
specifications only, and when previously prepared drawings are
amended but not noted on all file drawings
●● 24. Site preparation information is provided on the _______ plan.
Answer: Site
●● 25. The electrical contractor is responsible for all site _______.
Answer: Excavation, surface repair, and pumping
●● 26. To avoid incurring additional costs due to broken lines,
underground wires and utilities must be located _______.
Answer: Before digging
COMPLETE QUESTIONS AND ANSWERS
GRADED A PLUS
●● 2. Raceways are taken off per _____. Fittings required to make turns
and extensions are taking off per _____.
Answer: Linear foot, each
●● 3. All wires and conductors are taken off per _____.
Answer: Linear foot
●● 4. All fittings, devices and boxes are taken off per _____.
Answer: Each Item
●● 5. Permits and fees for tie-ins may be listed at lump sum and are
taken off per _____.
Answer: Occurrence,Project, and Contract
●● 6. Control stations are taken off by _______.
Answer: Individual Unit and Each Item.
●● 7. Panelboards are taken off individually according to ______.
,Answer: Type, Size, and Voltage
●● 8. Starters, safety switches and fuses are taken off per _______.
Answer: Each Item
●● 9. _______ should be kept separate from general light fixtures.
Answer: Exit Lighting
●● 10. Interior and exterior lighting should be taken off and listed
_______.
Answer: Separately
●● 11. Lamps for light fixtures are _______.
Answer: Taken off per each Item
●● 12. Light fixtures should be listed in the takeoff according to
_______.
Answer: Color
●● 13. Working electrical drawings numbered sequentially, prefaced by
the letter "E", include _______.
Answer: Telecommunications and security systems only
,●● 14. The _______ shows power requirements of the structure.
Answer: Power plan
●● 15. The _______ aids the electrical contractor sizing the panel.
Answer: Panel Schedule
●● 16. The _______ plan is supplemented by the fixture schedule.
Answer: Lighting
●● 17. The fixture schedule lists lamp _______.
Answer: Wattage
●● 18. Electrical specifications provide _______.
Answer: The grade of materials to be used, Materials installation
specifics, and how materials will be used in the finished system
●● 19. _______ must be maintained by the electrical contractor for all
installed work.
Answer: As-built drawings
●● 20. No conductors are smaller than No. _______ wire.
Answer: 12
, ●● 21. _______ Shall be installed in service entrances and panel feeders.
Answer: Rigid conduit
●● 22. The electrical contractor is responsible for providing and
installing _______ for a complete telephone system.
Answer: Outlet boxes, pull boxes, and empty raceways
●● 23. Interpretation of construction drawings and specifications may
conflict when _______.
Answer: Standard specifications are used with specific working plans,
previously prepared plans are changed and referenced in the
specifications only, and when previously prepared drawings are
amended but not noted on all file drawings
●● 24. Site preparation information is provided on the _______ plan.
Answer: Site
●● 25. The electrical contractor is responsible for all site _______.
Answer: Excavation, surface repair, and pumping
●● 26. To avoid incurring additional costs due to broken lines,
underground wires and utilities must be located _______.
Answer: Before digging