ISA BMPs provide a practical guide for implementing __________ __________. - Answers industry
standards
NERC standards are specific to what line voltages? - Answers 200 kV & above
NERC standards require the reporting of all tree caused outages by __________ categories - Answers
three
Trees growing into contact with a single-phase distribution conductor pose __________ threat of a
tree-ground fault. - Answers little
Clearing for a new distribution line is likely to be paid for by a __________ budget. - Answers capital
A grid-based scheduling system is most likely to be used by highly __________ utilities. - Answers
urbanized
A challenge with grid-based scheduling is that circuits may traverse many grids, allowing for a variety
of __________ __________. - Answers tree conditions
The most expensive way to schedule work is: - Answers hotspotting
A contractor is paid for each tree pruned or removed when contracted using a __________
__________ contract. - Answers unit price
Communication between vegetation managers, contractors, supervisors, & workers should be both
__________ & __________. - Answers written & verbal
Long-term planning is __________, while short-term planning is __________. - Answers strategic;
tactical
__________ are documents that describe, instruct, & direct work results. - Answers specifications
Research has shown that trees are more likely to cause outages on __________-phase lines than on
__________-phase lines. - Answers three;
single
A results-based strategy designed to target trees as close as possible to the time that they interfere
with facilities is known as __________-__________-__________ management. - Answers just-in-time
A __________ __________ structure is a prioritized outline of job components that must be
completed for a successful project outcome. - Answers work breakdown
For most utilities, vegetation management departments are considered __________ __________ that
do not generate income. - Answers cost centers
Purchases of equipment or line construction are considered __________ expenses, whereas supply or
salaries are considered __________ expenses. - Answers capital;
operating
Time & material contracts are generally __________ risk factors for contractors & __________ risk for
utilities. - Answers low;
high
__________ __________ contracts are gaining popularity because the responsibility for productivity,
work planning, & scheduling rests with the contractor. - Answers unit price
Depreciation can be either __________-__________, in which costs are spread out over a lifetime of
an item, or __________, in which the amount of depreciation taken is higher immediately after the
purchase of an item. - Answers straight-line;
accelerated
True or False?
All of the following are approaches to work planning:
- Cycle-based
- Results-based
- Crisis management - Answers true
SWOT analysis is a strategic planning tool & an acronym, meaning: - Answers Strengths, Weaknesses,
Opportunities, Threats
Relative to the cost of routine maintenance, reactive maintenance can cost __________ times as
much. - Answers five
What are the three parts to the constraint triangle? - Answers time, cost, & scope
With respect to personnel management, what is the most common reason that people leave jobs? -
Answers treatment from supervisors