The critical path describes:



A.

Parts that must be ordered so that the project is finished on time

B.

The best way to do the work on the project

C.

Difficult tasks in the project

D.

The tasks that set the time needed to complete the project - ANSWERSD.

The tasks that set the time needed to complete the project



To create a schedule, you should estimate the time needed to complete the work shown at which level of the WBS?



A.

Lowest level

B.

Second level

C.

All levels

D.

Top...