Tentamen (uitwerkingen)
DBIA: Principles of Design-Build and Post Award & Contracts Questions and Answers 100% Solved
DBIA: Principles of Design-Build and Post 
Award & Contracts Questions and Answers 
100% Solved 
Cost Plus Fee Contract Format - contractor reimbursed for actual cost plus an agreed 
upon percentage 
GMP (Guaranteed Maximum Price) Contract Format - Combines Cost-Plus & Lump-Sum, 
contractor reimbursed for actual cost plus a fee only up to a certain amount.
Tentamen (uitwerkingen)
DBIA - Project Delivery - True or False Questions with Complete Solutions
PopulairDBIA - Project Delivery - True or False 
Questions with Complete Solutions 
Under the CM @ Risk delivery system, any sub-contractors hired to work on the project will 
enter into contract directly with the owner. T/F? False 
Design - Build delivers equal or higher quality than DBB projects according to a comparative 
study by CII and Penn State. T/F? True 
In a GMP contract approach/payment the Owner and DB entity share the costs in excess of the 
GMP established by the DB entity. T/F? False
Voordeelbundel
Dbia Exam Pack With Complete Solutions
DBIA - Principles of Design-Build and Post Award Questions and Answers 100% Solved

2
Exam (elaborations)
DBIA - Principles of DB & Post Award - True or False Questions with Complete Solutions

3
Exam (elaborations)
DBIA - Project Delivery - True or False Questions with Complete Solutions

4
Exam (elaborations)
DBIA – Chapters Questions and Answers
Tentamen (uitwerkingen)
DBIA – Contracts Questions and Answers Verified by Experts
DBIA – Contracts Questions and Answers 
Verified by Experts 
Risk Analysis Process Get everyone in the same room, discuss unique risks to project and 
then create a spreadsheet that describes each and determines who can best address with: 
insurance, management of risk, pricing and acceptance of risk. 
Risks to Design Build - Performance Specifications 
- Evolving Basis of Design 
- Risk of early termination & ownership of documents 
Course of Performance Asks what was the Intent and what h...
Tentamen (uitwerkingen)
DBIA - Project Delivery Questions and Answers DBIA - Project Delivery Questions and Answers Verified by Experts
DBIA - Project Delivery Questions and Answers 
Verified by Experts 
Contractor Led The most common DB entity structural arrangement? 
1 - Contractor 
2 - Architect What contracts does the owner holds in a CM @ Risk delivery method. 
Qualifications and Best Price How architect/engineering firms are typically selected?
Tentamen (uitwerkingen)
DBIA Team Questions and Answers 100% Solved
DBIA Team Questions and Answers 100% 
Solved 
Construction Manager Most resembles typical PM role, must support all team members 
in the field they must also now implement the design in the field. 
Integrated Project Leader (IPL) Performs duties of a traditional design build project 
manager as well as supporting the team in it's efforts to achieve an integrated, comprehensive 
solution that meets or exceeds the owners expectations. 
Design Build Project Manager (DM-PM) Traditional PM res...
Tentamen (uitwerkingen)
DBIA – Chapters Questions and Answers 100% Solved
DBIA – Chapters Questions and Answers 100% 
Solved 
Alliance Contracting Similar to relational contracting. Cooperative model that aligns 
values, goals and objectives between owners, designers and contractors. 
How faster delivery is achieved with Design Build: Overlapping Design and Construction 
so project can start while still designing. Less RFIs by the time you reach the field as problems 
have been sorted out in design. 
Disadvantages of Design Build Not typical = Steep Learning Cur...
Tentamen (uitwerkingen)
DBIA - Principles of DB & Post Award - True or False Questions with Complete Solutions
DBIA - Principles of DB & Post Award - True or 
False Questions with Complete Solutions 
A feasibility estimate established whether the project and scope of work is economically and 
financially within the client's means. True 
The best time to employ value engineering is after the design is complete. Flase 
"Choosing by Advantages" is an evaluation process sed to select between options by 
considering both the advantages and disadvantages of any given solution. False
Tentamen (uitwerkingen)
DBIA - Principles of Design-Build and Post Award Questions and Answers 100% Solved
DBIA - Principles of Design-Build and Post 
Award Questions and Answers 100% Solved 
Performance Requirement A requirement the expressed the owner's needs and expected 
operation of the end product. 
Certificate of Errors and Omissions Insurance NOT included in the basis of design 
documents. 
Basis of Design Documents Owner's Project Criteria (RFP), Deviation List, Design-Builder's 
Proposal