Solved
Alliance Contracting Similar to relational contracting. Cooperative model that aligns
values, goals and objectives between owners, designers and contractors.
How faster delivery is achieved with Design Build: Overlapping Design and Construction
so project can start while still designing. Less RFIs by the time you reach the field as problems
have been sorted out in design.
Disadvantages of Design Build Not typical = Steep Learning Curve, Owners must make
decisions earlier, Restrictive procurement regulations.
Best Value Procurement Quantitative (Cost) and Qualitative (Past Performance, Design
Solutions, Overall Management)
How to measure project success typically: Cost, Schedule, Quality
, How to measure project success in DB: Number of Innovative Solutions
Design Build Plus When Owners "Add-On" Extra Services such as: project financing,
project operations, maintenance and/or ownership.
3 Things to Consider before choosing a Project Delivery Method: Goals of Project,
Contraints/Limitations, Intangible Impacts.
Project Goals Budget, Schedule, Quality, Performance, Image, Appearance, Aesthetics,
Function.
Project Delivery Constraints Zoning, Licensing Requirements, Owners in house
capabilities and chain of command.
Project Delivery Intangible Impacts Corporate Culture, Personalities, Market Conditions,
Union Influence, Risk/Decision Making Comfort.
Important Characteristics to Design Build Delivery 1 - Solicitation/Basis of Award