The text refers to four basic project delivery systems they are: - ANSWERS1) Design Build

2) Design-Bid-Build

3) CM-at-risk

4)CM Agency



The three primary contractual principal parties involved are the: - ANSWERSArchitect, Owner, Contractor



The text lists three bidding procedures and contracts for contractors to obtain work: - ANSWERSCompetitive bid - low # wins (public works)

Unit Price - Marketing, relationships, reputation, preconstruction services, incomplete documents

 Negotiated ...