Bailey Bridge PE / BAILEY BRIDGE EXAM
QUESTIONS AND ANSWERS
Task 1: Which of the following are details included within the bridge assembly
party? - ---✔✔✔ANSWER----all
Task 2: Which duties are each assembly party detail responsible for completing? -
---✔✔✔ANSWER----Decking Detail
b.
Lay stringers, chess, and ribbands on bridge
Transom Detail
, a.
Carry, place and clamp down transoms
Bracing Detail
c.
Obtain, install, and adjust sway braces, rakers, and bracing frames
Panel Detail
d.
Carry, place and pin together panels in the launching nose and bridge
Task 3: Each unloading party consists of one noncommissioned officer and ___
soldiers. - ---✔✔✔ANSWER----8
Task 1: In what order should your unit assemble the launching nose of the bridge?
- ---✔✔✔ANSWER----place panels
connect second bay
place sway braces
rocking rollers
When placing the panels on the ground behind the rocking rollers, should the
female or male ends be placed forward? - ---✔✔✔ANSWER----female
QUESTIONS AND ANSWERS
Task 1: Which of the following are details included within the bridge assembly
party? - ---✔✔✔ANSWER----all
Task 2: Which duties are each assembly party detail responsible for completing? -
---✔✔✔ANSWER----Decking Detail
b.
Lay stringers, chess, and ribbands on bridge
Transom Detail
, a.
Carry, place and clamp down transoms
Bracing Detail
c.
Obtain, install, and adjust sway braces, rakers, and bracing frames
Panel Detail
d.
Carry, place and pin together panels in the launching nose and bridge
Task 3: Each unloading party consists of one noncommissioned officer and ___
soldiers. - ---✔✔✔ANSWER----8
Task 1: In what order should your unit assemble the launching nose of the bridge?
- ---✔✔✔ANSWER----place panels
connect second bay
place sway braces
rocking rollers
When placing the panels on the ground behind the rocking rollers, should the
female or male ends be placed forward? - ---✔✔✔ANSWER----female