CCM EXAM STUDY GUIDE HPM QUESTIONS AND VERIFIED ANSWERS

Document preview thumbnail
Preview 4 out of 120 pages

CCM EXAM STUDY GUIDE HPM QUESTIONS AND VERIFIED ANSWERS

Content preview

The agent CM is managing a contract that installs interior finish work for an
underground pedestrian tunnel. The concrete shell was constructed under another
contract over a year ago. The shell contract specified embeds in the cast-in-place
ceilings for hanging all-threads to support chilled water pipes. The finish contractor
has discovered that only expansion anchors were installed, which will not support the
pipe weight. He proposes a cost change to retrofit embeds using epoxy. The CM
learns that the tunnel shell designer approved the shell contractor's submittal for the
expansion anchors. Which of the following is the CM's best course of action?


a. Issue a change order to the finish contractor for the epoxy embeds. Seek to
recover the designer or shell contractor
b. Contact the shell designer to design and contrite the repair based on the submittal

,approval in error
c. Contact the shell contractor to retrofit based on a latent defect
d. Ask a third-party task order contractor to design and install the retrofit with that
charge to the shell contractor and shell designer in proportion to their contract dollar
values


Give this one a try later!


c. Contact the shell contractor to retrofit based on a latent defect




SCHEDULE REVISIONS CM's role


Give this one a try later!


1. CM must recognize need for revision to PROJECT PLAN & provide owner
w/ Recommendations how to address.
2. Once team recognized revisions needed to plan. CM's responsibilities
-CM itself responsible develop schedule w/ subs revisions
- CM keeps owner informed
- CM reviews submissions
- CM shifts focus to revised schedule for project teams performance
monitoring.
- CM reviews updated schedule. Determines it defines plan for completion
of remaining project work.
3. GC req. time extension. CM's verifies in accordance w/ contract
provisions.
-CM ensures analysis for magnitude of the delay
- CM reviews time extension in accordance
- CM makes recommendations
- At-Risk CM may be allowable by contract for additional time for itself .




The owner has requested that the project to be completed by April 13th. Based on the
schedule network diagram provided, will be the project be completed on time?

,a. Yes
b. No


Give this one a try later!




The occupancy plan is a means to plan and coordinate the time frame between the
construction phase and______.


a. Operation/use phase
b. Final payment
c. Final punch list completion
d. Demobilization


Give this one a try later!


a. Operation/use phase




A design-bid-build project is ready to begin the procurement process, but the owner
is worried about receiving unbalanced bids. The owner also wants to avoid delays
and disputes. Which of the following will BEST accomplish the owner's goals?


Give this one a try later!


a. If any bids are unbalanced, reject all bids and rebid the project
b. Reject the apparent low bidder if the bid appears unbalanced
c. Allow the apparent low bidder to rebalance if the bid appears

, unbalanced
d. Include a mobilization payment line item in the bid form




What does ES mean in a diagram?


Give this one a try later!


Early Start




Which of the following constitutes unethical behavior for a construction management
firm during the administration of the project?


a. Assigning unqualified staff
b. Overstating the firm's credentials
c. Offering persons that you don't have
d. Selling services that you do not plan to deliver


Give this one a try later!


d. Selling services that you do not plan to deliver




Safety Mngmt - CM hired for safety mngmt


Give this one a try later!


Separate contract w/ owner required

Clearly defined scope/ compensation


CM Liability projection cost must be covered

Document information

Uploaded on
December 12, 2025
Number of pages
120
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$10.50

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
BestKey
4.3
(116)
Sold
278
Followers
108
Items
8363
Last sold
1 week ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions