◍ Develop Project Charter Tools & Techniques x. Answer: Expert
judgement, data gathering, interpersonal & team skills, and meetings.
x
◍ Develop Project Charter Outputs. Answer: Project Charter,
Assumption log
◍ Develop PM Plan Inputs. Answer: Proj. charter, outputs from other
processes, Enterprise enviro. factors, and Org. process assets
◍ Develop PM Plan Tool & Techniques. Answer: Expert judgement,
data gathering, interpersonal and team skills, and meetings
◍ Develop PM Plan Outputs. Answer: PM Plan
◍ Direct and Manage Project Work, Inputs. Answer: PM plan, proj.
docs, approved change requests, enterprise enviro. factors, and org.
process assets
,◍ Direct and Manage Project Work, Tools & Techniques. Answer:
Expert judgement, PMIS, and meetings
◍ Direct and Manage Project Work, Outputs. Answer: Deliverables,
work performance data, issue log, change requests, PM plan updates,
proj. docs. updates, and org. process assets updates
◍ Manage Project Knowledge, Inputs. Answer: PM plan, proj. docs.,
deliverables, enterprise enviro. factors, and org. process assets
◍ Manage Project Knowledge, Tools & Techniques. Answer: Expert
judgement, knowledge management, information management,
interpersonal & team skills
◍ Manage Project Knowledge, Outputs. Answer: Lessons learned
register, PM plan updates, and org. process assets updates
◍ Monitor and Control Project Work, Inputs. Answer: PM plan, proj.
docs, work performance information, agreements, enter. enviro.
factors, and org. process assets
◍ Monitor and Control Project Work, Tools and Techniques. Answer:
Expert judgement, data analysis, decision making, and meetings
◍ Monitor and Control Project Work, Outputs. Answer: Work
performance reports, change requests, PM plan updates, and proj.
docs updates
, ◍ Perform Integrated Change Control, Inputs. Answer: PM plan, proj.
docs, work performance reports, change requests, enter. enviro.
factors, and org. process assets
◍ Perform Integrated Change Control, Tools & Techniques. Answer:
Expert judgement, change control tools, data analysis, decision
making, and meetings
◍ Perform Integrated Change Control, Outputs. Answer: Approved
change requests, PM plan updates, and proj. documents updates.
◍ Close Project or Phase, Inputs. Answer: Project charter, PM plan,
pro. docs, accepted deliverables, business docs, agreements,
procurement docs, and org. process assets
◍ Close Project or Phase, Tools & Techniques. Answer: Expert
Judgement
Analytical Techniques
Meetings
◍ Close Project or Phase, Outputs. Answer: Project document
updates, Final product/service/result transition, Final report, OPA
updates
◍ Plan Scope Management, Inputs. Answer: Project Charter, Project
Management Plan, EEFs, OPAs