Project Resource Management includes all of the following processes except:
Plan RM
Acquire project team
Manage project team
Delegate project team - Correct answer-Delegate project team
The process of confirming resource availability and obtaining the team necessary is
_____.
acquire team
develop team
delegate team
©COPYRIGHT 2025, ALL RIGHTS RESERVED 1
,train team - Correct answer-acquire team
The key benefit of the Plan RM process is that it:
establishes project roles & responsibilities
establishes organization charts
establishes the staffing management plan
All of the above - Correct answer-All of the above
Types of charts that a PM can use as a tool in RM include ____ charts.
regressional
hierarchical
forward-leaning
PDCA - Correct answer-hierarchical
The "I" in a traditional responsibility matrix chart stands for:
Inspect
©COPYRIGHT 2025, ALL RIGHTS RESERVED 2
,Inform
Inquire
Inane - Correct answer-Inform
What is the key output of Plan RM?
Deliverable-oriented standards
An established project team
The Resource Management Plan
the Work Breakdown Structure - Correct answer-The Resource Management Plan
"What is expected as a completed duty" is the best definition for _____.
responsibility
competency
role
authority - Correct answer-responsibility
©COPYRIGHT 2025, ALL RIGHTS RESERVED 3
, The staffing management plan includes items such as resource calendars, training
needs, and _____.
staff release plan
recognition and rewards
neither a or b
both a and b - Correct answer-both a and b
_____ is a tool that the PM and his/her team can use to acquire staff.
Negotiation
HRM
Staffing
Charting - Correct answer-Negotiation
Which of the following is NOT an advantage of the virtual team?
incorporate employees who work from home
©COPYRIGHT 2025, ALL RIGHTS RESERVED 4
Answers Graded A+
Project Resource Management includes all of the following processes except:
Plan RM
Acquire project team
Manage project team
Delegate project team - Correct answer-Delegate project team
The process of confirming resource availability and obtaining the team necessary is
_____.
acquire team
develop team
delegate team
©COPYRIGHT 2025, ALL RIGHTS RESERVED 1
,train team - Correct answer-acquire team
The key benefit of the Plan RM process is that it:
establishes project roles & responsibilities
establishes organization charts
establishes the staffing management plan
All of the above - Correct answer-All of the above
Types of charts that a PM can use as a tool in RM include ____ charts.
regressional
hierarchical
forward-leaning
PDCA - Correct answer-hierarchical
The "I" in a traditional responsibility matrix chart stands for:
Inspect
©COPYRIGHT 2025, ALL RIGHTS RESERVED 2
,Inform
Inquire
Inane - Correct answer-Inform
What is the key output of Plan RM?
Deliverable-oriented standards
An established project team
The Resource Management Plan
the Work Breakdown Structure - Correct answer-The Resource Management Plan
"What is expected as a completed duty" is the best definition for _____.
responsibility
competency
role
authority - Correct answer-responsibility
©COPYRIGHT 2025, ALL RIGHTS RESERVED 3
, The staffing management plan includes items such as resource calendars, training
needs, and _____.
staff release plan
recognition and rewards
neither a or b
both a and b - Correct answer-both a and b
_____ is a tool that the PM and his/her team can use to acquire staff.
Negotiation
HRM
Staffing
Charting - Correct answer-Negotiation
Which of the following is NOT an advantage of the virtual team?
incorporate employees who work from home
©COPYRIGHT 2025, ALL RIGHTS RESERVED 4