The ______ consists of daily checks of the work to assure
continuing compliance with contract requirements ANS >> Follow-
up phase
Design-Build contracts require: ANS >> *The QC Manager to be in
place and take an active role in the review and coordination of
the design*
Which of the following is included in all three phases of the
Three Phases of Control ANS >> Safety
, The purpose of Construction Quality Management is to ANS >>
*Achieve the quality established by properly developed
requirements through the combined responsibility, but separate,
efforts of contractor and Government personnel*
Testing is extremely important in Construction Quality
Management and is performed by ANS >> Both the contractor and
the Government
The primary purpose of the Three-Phase Control System is to:
ANS >> Require the contractor to plan, schedule, and perform
quality management actions to assure work meets all specified
quality standards
Quality Assurance Personnel have the responsibility to: ANS >>
*require the contractor to maintain the quality specified in the
plans and specifications*
the ____ is the appropriate time to assure that all materials
and/or equipment have been tested. submitted, and approved.
ANS >> Preparatory Phase