ANSWERS|LATEST
UPDATE!!!!2025/2026|GUARANTEED
While field testing the check valve of a pressure vacuum breaker, water continues to flow
from the # 2 test cock . How do you proceed ? - ANSWER Open the bleed off valve
until the flow slows to a slight drip.
Well field testing the first check valve of a double check valve assembly, water continues to
flow from the site tube. How do you proceed? - ANSWER Observe reading on gauge
(first step). Open high side of bleed valve (second step).
While field testing the check valve of a spill resistant pressure vacuum breaker, water
continues to flow from the vent valve. What does this imply? - ANSWER Number 1
shut off valve is leaking.
While field testing the differential pressure relief valve opening point of RP, it is found that
the shut - off valve # 2 is leaking . How should the temporary bypass hose be connected to
compensate for the leak? - ANSWER Test cock # 1 to test cock # 4
While field testing the second check valve of a reduced pressure principle assembly, high
side pressure is applied through test cock # 4 and the gage reading begins to increase. How
do you proceed? - ANSWER Close the # 2 test cock.
While field testing the differential pressure relief valve opening point of an RP, the high side
control needle valve is open, and the low side control needle valve is open 1/4 turn,
however the reading on the gauge will not lower to the relief valve opening point. What
does this imply? - ANSWER Number 2 shut off valve is leaking
1