Initializing Master Tasks does two things:
✓ Links the Master Task to the Maintenance Procedure.
✓ Activates the Maintenance Task that will be put in the Maintenance Scheduler.
For local procedures, the Maintenance Procedure number prefix is:
✓ L-xxxx.
Master Tasks that have a periodicity of "Conditional" are not automatically added
to the schedule because:
✓ They are not due until a certain "condition" is attained.
A Unit Operation Schedule must be created before:
✓ The Maintenance Schedule can be populated. This is an annual task usually
performed at the beginning of the calendar year.
If the Annual Schedule has not been propagated, the following message is
displayed:
✓ "SINGLE USER MODE should be enabled before running the annual schedule
propagation for the chosen period. Are you in single user mode? Yes or No?"
Unless your System Administrator has set up CMplus in single-user mode,
respond "No" to the prompt.
What is the purpose of creating a Local Maintenance Procedure in CMplus for a
piece of equipment? -ANSWER✔✔Local Maintenance Procedures are created to
meet the specific needs of a local unit for procedures not included in the official
Preventive Maintenance System (PMS) Schedule.
,What is accomplished in CMplus by initializing a Master Task? -
ANSWER✔✔Initializing Master Tasks does two things:
Links the Master Task to the Maintenance Procedure.
Activates the Maintenance Task which will be put in the Maintenance Scheduler
You are assigning a Local Maintenance Task to a Maintenance Schedule. What
procedure is accomplished after the "Schdule Task" prompt is displayed? -
ANSWER✔✔Enter the date on which this task will be accomplished and press
F10 or click the OK icon
Creating a Unit Operations Schedule is necessary before the _____. -
ANSWER✔✔Maintenance Schedule can be populated
What message will be displayed if a calendar for a specific year has been created,
but no items have been scheduled for maintenance? -ANSWER✔✔There are no
scheduled items of the specific type.
You are creating a Maintenance Procedure Detail. What action is required when
the Maintenance Procedure Selection screen is displayed? -ANSWER✔✔Select a
procedure to be updated from the list and choose Update from the Edit menu or
click the update icon
To ensure consistency within the system, any updates or changes to the Local
Maintenance Procedures must be applied to the ________. -ANSWER✔✔Master
Tasks
,You are updating the Local Maintenance Task. What is the purpose of the
Maintenance Task Detail screen? -ANSWER✔✔This would allow you to add new
or updated information to be entered into any of the following fields:
Work Center.
Priority.
Due at Hours.
Est. Labor Hours.
Task Description.
Special Instructions.
You are creating a Local Maintenance Procedure in CMplus. Which field identifies
the frequency of the task?
A. Estimated Workforce Hours
B. Periodicity
C. Description
D. Type -ANSWER✔✔B
Initializing the Master Task will activate the Maintenance Task, which will be put
in the Maintenance Scheduler, and will also _____.
A. link the Master Task to the Maintenance field
B. link the Master Task to the Periodicity field
C. propagate a Unit Maintenance Schedule
D. link the Master Task to the Maintenance Procedure -ANSWER✔✔D
After you have opened the Maintenance Schedule when assigning a Local
Maintenance Task to the Maintenance Schedule, you will need to ensure that you
are in the _____.
, A. Update mode
B. Options mode
C. Edit menu
D. Report category -ANSWER✔✔A
The Unit Operation Schedule is used to _____.
A. assign a Maintenance Task
B. provide an overview of the unit's operating schedule
C. assign the work centers at a unit
D. assign billets -ANSWER✔✔B
When creating a Maintenance Schedule, the FIRST thing that you should choose
from the Maintenance menu is _____.
A. Maintenance Task
B. Unit option
C. Schedules
D. Work Centers -ANSWER✔✔C
Adding or editing detailed information on an update of a Local Maintenance
Procedure includes _____.
A. transfer of the CI
B. procedure number
C. consumables
D. environmental concerns -ANSWER✔✔C
AND ANSWERS WITH COMPLETE
SOLUTIONS 100% CORRECT!!!
Initializing Master Tasks does two things:
✓ Links the Master Task to the Maintenance Procedure.
✓ Activates the Maintenance Task that will be put in the Maintenance Scheduler.
For local procedures, the Maintenance Procedure number prefix is:
✓ L-xxxx.
Master Tasks that have a periodicity of "Conditional" are not automatically added
to the schedule because:
✓ They are not due until a certain "condition" is attained.
A Unit Operation Schedule must be created before:
✓ The Maintenance Schedule can be populated. This is an annual task usually
performed at the beginning of the calendar year.
If the Annual Schedule has not been propagated, the following message is
displayed:
✓ "SINGLE USER MODE should be enabled before running the annual schedule
propagation for the chosen period. Are you in single user mode? Yes or No?"
Unless your System Administrator has set up CMplus in single-user mode,
respond "No" to the prompt.
What is the purpose of creating a Local Maintenance Procedure in CMplus for a
piece of equipment? -ANSWER✔✔Local Maintenance Procedures are created to
meet the specific needs of a local unit for procedures not included in the official
Preventive Maintenance System (PMS) Schedule.
,What is accomplished in CMplus by initializing a Master Task? -
ANSWER✔✔Initializing Master Tasks does two things:
Links the Master Task to the Maintenance Procedure.
Activates the Maintenance Task which will be put in the Maintenance Scheduler
You are assigning a Local Maintenance Task to a Maintenance Schedule. What
procedure is accomplished after the "Schdule Task" prompt is displayed? -
ANSWER✔✔Enter the date on which this task will be accomplished and press
F10 or click the OK icon
Creating a Unit Operations Schedule is necessary before the _____. -
ANSWER✔✔Maintenance Schedule can be populated
What message will be displayed if a calendar for a specific year has been created,
but no items have been scheduled for maintenance? -ANSWER✔✔There are no
scheduled items of the specific type.
You are creating a Maintenance Procedure Detail. What action is required when
the Maintenance Procedure Selection screen is displayed? -ANSWER✔✔Select a
procedure to be updated from the list and choose Update from the Edit menu or
click the update icon
To ensure consistency within the system, any updates or changes to the Local
Maintenance Procedures must be applied to the ________. -ANSWER✔✔Master
Tasks
,You are updating the Local Maintenance Task. What is the purpose of the
Maintenance Task Detail screen? -ANSWER✔✔This would allow you to add new
or updated information to be entered into any of the following fields:
Work Center.
Priority.
Due at Hours.
Est. Labor Hours.
Task Description.
Special Instructions.
You are creating a Local Maintenance Procedure in CMplus. Which field identifies
the frequency of the task?
A. Estimated Workforce Hours
B. Periodicity
C. Description
D. Type -ANSWER✔✔B
Initializing the Master Task will activate the Maintenance Task, which will be put
in the Maintenance Scheduler, and will also _____.
A. link the Master Task to the Maintenance field
B. link the Master Task to the Periodicity field
C. propagate a Unit Maintenance Schedule
D. link the Master Task to the Maintenance Procedure -ANSWER✔✔D
After you have opened the Maintenance Schedule when assigning a Local
Maintenance Task to the Maintenance Schedule, you will need to ensure that you
are in the _____.
, A. Update mode
B. Options mode
C. Edit menu
D. Report category -ANSWER✔✔A
The Unit Operation Schedule is used to _____.
A. assign a Maintenance Task
B. provide an overview of the unit's operating schedule
C. assign the work centers at a unit
D. assign billets -ANSWER✔✔B
When creating a Maintenance Schedule, the FIRST thing that you should choose
from the Maintenance menu is _____.
A. Maintenance Task
B. Unit option
C. Schedules
D. Work Centers -ANSWER✔✔C
Adding or editing detailed information on an update of a Local Maintenance
Procedure includes _____.
A. transfer of the CI
B. procedure number
C. consumables
D. environmental concerns -ANSWER✔✔C