UPDATED CLC 222 MODULE 5 TEST 2026
CONTRACT MONITORING AND HANDLING
ISSUES QUESTIONS WITH ACCURATE
SOLUTIONS
◉ during communications with the contractor the COR may Answer:
provide clarification about concerns or issues
◉ The COR may release information without consulting with the
Contracting Officer or Legal Counsel. Answer: false
◉ when dealing with noncompliance what is the most preferred
solution Answer: Have the contractor repair or replace the defective
or non-conforming supplies, or reperform the non conforming
services at no additional cost
◉ If a contractor is delinquent on a portion of a contract, and that
portion is clearly severable from the continuing portion of the
contract, the Contracting Officer may terminate the deficient portion
of the contract using a Partial Termination. Answer: True
CONTRACT MONITORING AND HANDLING
ISSUES QUESTIONS WITH ACCURATE
SOLUTIONS
◉ during communications with the contractor the COR may Answer:
provide clarification about concerns or issues
◉ The COR may release information without consulting with the
Contracting Officer or Legal Counsel. Answer: false
◉ when dealing with noncompliance what is the most preferred
solution Answer: Have the contractor repair or replace the defective
or non-conforming supplies, or reperform the non conforming
services at no additional cost
◉ If a contractor is delinquent on a portion of a contract, and that
portion is clearly severable from the continuing portion of the
contract, the Contracting Officer may terminate the deficient portion
of the contract using a Partial Termination. Answer: True