1. The process of establishing clear and achievable objectives, measuring
their achievement, and adjusting performance in accordance with the
results of the measurement is called: - correct answer- Management
by Objectives
100. Your project manager has decided on the ideal project
management team and sketched out an informal plan to begin
recruiting. He has also decided that it will be best to lease temporary
office space, to serve as project headquarters for the team. Establishing
an office facility like this for the team to work in close proximity is an
example of what? - correct answer- Collocation
101. Which of the following is NOT a tool and technique for the 'Acquire
Project Team' process? - correct answer- Resource calendars
102. Team development will be MOST difficult to achieve under which of
the following conditions? - correct answer- When team members
are accountable to both - project manager and functional manager
103. The five stages of development of teams is represented by - -
correct answer- Forming, Storming, Norming, Performing, Adjourning
,104. Which of the following is NOT an input to the 'Develop Human
Resource Plan'? - correct answer- Expert Judgment
105. Which of the following is TRUE about Progress Reports, a report
that informs the stakeholders about the progress of the project? -
correct answer- They allow stakeholders to judge the performance of
the project according to its plan
106. The three principal interests in maintaining good document control
are: - correct answer- Effective communication, ability to reconstruct
why decisions were made and historical value
107. Your project manager wants to handle communications well in his
project. In order to do this he has chosen to write a communications
plan. Of the items listed below, which one is not part of the
communications plan? - correct answer- Project organizational
structure
108. Which of the following techniques allows for the participants to be
anonymous? - correct answer- Delphi technique
109. In the communications model, communications between the
sender and the receiver often are affected by communications barriers.
These include all of the following except: - correct answer- Lack of a
communications device
, 11. A group of related projects that are managed in a coordinated way
that usually includes an element of ongoing activity is called a: - correct
answer- Program
110. Formal written communication with the customer is required
when : - correct answer- Customer requests some additional work
not covered under the contract
111. When you want to report on the actual project results vs. planned
results, you use? - correct answer- Variance report
112. The Power /interest grid groups the stakeholders based on - -
correct answer- Level of authority (power) and their level of concern
(interest) .
113. Which of the following is NOT an input to the 'Plan
Communications' process? - correct answer- Communications
technology
114. You are attending the status meeting along with 7 other project
team members and the project manager. How many communication
channels are available in the status meeting? - correct answer- 36
116. Two vendors offer to sell similar electronic components, which are
integrated at the vendor's site. To avoid risk while evaluating the bids,