Practice Questions and Answers | Verified
and Updated
Toggle hangers shall be permitted only for the support of pipe __________ inches or smaller in
size under ceilings of hollow tile or metal lath and plaster. - answer-:1 2/2 in. (ref. NFPA 13 2016
Sec. 9.2.1.1.2.
While conducting a flow test, the chosen hydrant should be ______ - answer-:As close to the
property where the sprinkler system is being installed. (Ref, NFPA 13 Sec. A.24.2.2. or NFPA 291)
What type of information is collected when you are conducting a water flow test from one
hydrant? - answer-:Static and Residual Pressure
Refrence NFPA 13 2016
Section A.24.2.2.
Fire pump system plans are required to include which of the following: - answer-:Controller
manufacturer, type, and rating, Suction and discharge pipe and fittings, and Suction main size,
length, and location.
Reference NFPA 20 2016, Section 4.2.
,Which of the following must be included in the Working Plans associated with water supply
requirements? - answer-:Density, Area of water application, In-rack sprinkler demand, and
Inside and outside hose demand.
Reference NFPA 13 2016, Section 23.1.3(35).
NFPA 13 defines the information which should be included in the working plans to be submitted
to the AHJ for approval. These include which of the following: - answer-:Location, Occupancy
Classification, Location of concealed spaces, Area protected by each sprinkler, Number of
sprinklers.
Reference NFPA 13 2016, Section 23.1.3.
Who must sign the Owner's Certificate? - answer-:The owner or the owner's representative.
Reference NFPA 13 2016, Figure A.23.1(b). The Owner's Certificate declares the intended use of
the occupancy to be protected.
Water flow test info should be included on what set of plans? - answer-:The drawings that
accompany the Owner's Information Certificate.
Reference NFPA 13 2016, Section A.23.1.
The Owner's Information Certificate indicates the property to be protected will contain nitrate
film. Which of the following is also required to be pro - answer-:Type, arrangement, location,
and intended maximum quantities.
Reference NFPA 13 2016, Figure A.23.1(b).
, What is defined as measuring 12 inches or more in its least dimension in any floor, platform,
pavement, or yard? - answer-:A floor opening. It is an opening through which persons may fall.
Reference OSHA 29 CFR, Part 1910.21(a) (2).
_________ indicates a mandatory requirement according to NFPA definitions? - answer-:Shall.
Reference NFPA 13 2016, Section 3.2.4.
100 gpm is flowing through 100' of 1 1/4in Schedule 40 pipe. How many feet of 1 1/2in pipe will
produce the same friction loss? - answer-:Step #1: Assume this is Schedule 40 pipe, C = 120. Use
the Hazen-Williams formula to calculate the friction loss for the 1 ¼ in. pipe and the 1 ½ in. pipe.
For 1 ¼ in. pipe (ID = 1.38):
P friction loss = 4.52 x Q 1.85
c 1.85 x d 4.87
P friction loss = 4.52 x 100 1.85
120 1.85 x 1.38 4.87
P friction loss = 0.672 psi/ft