(IFGC)
appliance
(Section 101.2.2 Piping Systems) - ANSWERS-The IFGC covers gas
piping from the point of delivery to the outlet of the shutoff valves.
this code
(Section 102.8.1 Provisions in referenced codes and standards) -
ANSWERS-Where conflicts occur between the provisions of this code
and the referenced standards, the provisions of the __________
____________ shall apply.
modifications (Section 105.1 Modifications) - ANSWERS-Whenever
there are practical difficulties involved in carrying out the provisions of
this code, the code official shall have the authority to grant __________
for individual cases.
in writing,
reason for disapproval
END OF
PAGE
1
,International Fuel Gas Code LATEST
(IFGC)
(Section 105.2 Alternative materials, design and methods of construction
and equipment.) - ANSWERS-Where the code official finds that a
proposed alternative material does not comply with the intent of the code
provisions, the code official shall respond __________ __________
stating the __________ __________ _________.
next working
(section 106.1 Where required, Exception) - ANSWERS-Where
appliance and equipment replacements and repairs are required to be
performed in an emergency situation, the permit application shall be
submitted within the _________ ___________ business day of
Department of Inspection.
portable
(Section 106.2. Permits not required, Item 1.) - ANSWERS-Permits
shall not be required for any _________ heating appliance.
permit
END OF
PAGE
2
,International Fuel Gas Code LATEST
(IFGC)
(Section 106.5 Permit issuance) - ANSWERS-The application,
construction documents and other data filed by an applicant for a
__________ shall be reviewed by the code official.
180
(Section 106.5.3 Expiration, Section 106.5.4 Extensions) - ANSWERS-
Every permit issued by the code official under the provisions of this
code shall expire by limitation and become null and void if the work
authorized is not commenced within _____ days.
180
(Section 107.2 Retention of construction documents) - ANSWERS-One
set of approved construction documents shall be retained by the code
official for a period of not less than _____ days from the date of
completion of the permitted work, or as required by state or local laws.
inspection,
inspection
END OF
PAGE
3
, International Fuel Gas Code LATEST
(IFGC)
(Section 112.1 General) - ANSWERS-Construction or work for which a
permit is required shall be subject to _________ by the code official, and
such construction or work shall remain visible and able to be accessed
for __________ purposes until approved.
authorized
(Section 110.1 Connection of service utilities) - ANSWERS-A person
shall not make connections from a utility, source of energy, fuel or
power to any building or system that is regulated by this code for which
a permit is required until __________ by the code official.
Appliance
(Section 202 General definitions) - ANSWERS-Any apparatus or device
that utilizes a fuel or a raw material as a fuel to produce light, heat,
power, refrigeration or air conditioning.
Atmospheric Pressure
END OF
PAGE
4