WGU D521 NEWLY UPDATED COLLECTION OF EXAM QUESTIONS AND VERIFIED
ANSWERS DESIGNED TO GUARANTEE YOUR SUCCESS ON THE LATEST TEST
VERSION
Q1: What is a project? ANSWER A project is a temporary endeavor
undertaken to create a unique product, service, or result with a defined
beginning and end.
Q2: What distinguishes a project from operations? ANSWER Projects are
temporary and unique, while operations are ongoing and repetitive.
Q3: What are the five process groups in project management? ANSWER
Initiating, Planning, Executing, Monitoring and Controlling, and Closing.
Q4: What are the ten knowledge areas in PMBOK? ANSWER Integration,
Scope, Schedule, Cost, Quality, Resource, Communications, Risk, Procurement,
and Stakeholder Management.
Q5: What is a project charter? ANSWER A document that formally
authorizes a project and gives the project manager authority to apply resources.
Q6: What is the purpose of a business case? ANSWER To justify the
investment in a project by documenting the business need and expected
benefits.
Q7: What is stakeholder analysis? ANSWER The process of identifying
stakeholders and analyzing their interests, influence, and impact on the project.
Q8: What is a Work Breakdown Structure (WBS)? ANSWER A
hierarchical decomposition of the total scope of work to be carried out by the
project team.
Q9: What is the critical path? ANSWER The longest sequence of activities
in a project schedule that determines the minimum project duration.
Q10: What is scope creep? ANSWER The uncontrolled expansion of project
scope without adjustments to time, cost, and resources.
Q11: What is a milestone? ANSWER A significant point or event in a project
with zero duration that marks completion of a deliverable or phase.
Q12: What is the triple constraint? ANSWER The balance between scope,
time, and cost that defines project success.
,Q13: What is earned value management (EVM)? ANSWER A methodology
that combines scope, schedule, and resource measurements to assess project
performance.
Q14: What is a Gantt chart? ANSWER A bar chart that illustrates a project
schedule showing start and finish dates of project elements.
Q15: What is the difference between a risk and an issue? ANSWER A risk
is a potential future event that may impact the project; an issue is a current
problem requiring immediate attention.
Q16: What is resource leveling? ANSWER A technique to resolve resource
conflicts by adjusting start and finish dates based on resource constraints.
Q17: What is fast tracking? ANSWER A schedule compression technique
where activities normally done in sequence are performed in parallel.
Q18: What is crashing? ANSWER Adding resources to critical path activities
to reduce project duration.
Q19: What is a project baseline? ANSWER The approved version of scope,
schedule, and cost used as a reference for comparison.
Q20: What is change control? ANSWER A formal process to manage
changes to project documents, deliverables, or baselines.
Q21: What is a RACI matrix? ANSWER A responsibility assignment matrix
showing who is Responsible, Accountable, Consulted, and Informed for each
task.
Q22: What is quality assurance? ANSWER Process-oriented activities that
ensure the project will satisfy quality standards.
Q23: What is quality control? ANSWER Product-oriented activities that
verify deliverables meet quality requirements.
Q24: What is a risk register? ANSWER A document listing identified risks,
their probability, impact, and response strategies.
Q25: What is qualitative risk analysis? ANSWER Assessing risk probability
and impact using subjective scales to prioritize risks.
Q26: What is quantitative risk analysis? ANSWER Numerically analyzing
the effect of identified risks on project objectives.
Q27: What is a risk response strategy for threats? ANSWER Avoid,
Transfer, Mitigate, or Accept.
, Q28: What is a risk response strategy for opportunities? ANSWER Exploit,
Share, Enhance, or Accept.
Q29: What is procurement management? ANSWER The process of
purchasing or acquiring products, services, or results from outside the project
team.
Q30: What is a statement of work (SOW)? ANSWER A narrative
description of products, services, or results to be delivered by a vendor.
Q31: What is the difference between fixed-price and cost-reimbursable
contracts? ANSWER Fixed-price has a set price regardless of costs; cost-
reimbursable reimburses actual costs plus fee.
Q32: What is stakeholder engagement? ANSWER Activities to involve
stakeholders appropriately in project decisions and execution.
Q33: What is a communication plan? ANSWER A document defining who
needs what information, when, and through what channels.
Q34: What is scope validation? ANSWER The formal acceptance of
completed project deliverables by stakeholders.
Q35: What is a lessons learned register? ANSWER A document capturing
knowledge gained during the project for future reference.
Q36: What is project closure? ANSWER The final phase where project
activities are completed and formally closed.
Q37: What is float or slack? ANSWER The amount of time an activity can be
delayed without delaying the project.
Q38: What is the difference between leads and lags? ANSWER Leads allow
successor activities to start early; lags add waiting time between activities.
Q39: What is analogous estimating? ANSWER Using historical data from
similar projects to estimate duration or cost.
Q40: What is parametric estimating? ANSWER Using statistical
relationships between historical data and variables to calculate estimates.
Q41: What is bottom-up estimating? ANSWER Estimating work packages
individually and aggregating them to get total estimate.
Q42: What is three-point estimating? ANSWER Using optimistic,
pessimistic, and most likely estimates to calculate expected duration or cost.
ANSWERS DESIGNED TO GUARANTEE YOUR SUCCESS ON THE LATEST TEST
VERSION
Q1: What is a project? ANSWER A project is a temporary endeavor
undertaken to create a unique product, service, or result with a defined
beginning and end.
Q2: What distinguishes a project from operations? ANSWER Projects are
temporary and unique, while operations are ongoing and repetitive.
Q3: What are the five process groups in project management? ANSWER
Initiating, Planning, Executing, Monitoring and Controlling, and Closing.
Q4: What are the ten knowledge areas in PMBOK? ANSWER Integration,
Scope, Schedule, Cost, Quality, Resource, Communications, Risk, Procurement,
and Stakeholder Management.
Q5: What is a project charter? ANSWER A document that formally
authorizes a project and gives the project manager authority to apply resources.
Q6: What is the purpose of a business case? ANSWER To justify the
investment in a project by documenting the business need and expected
benefits.
Q7: What is stakeholder analysis? ANSWER The process of identifying
stakeholders and analyzing their interests, influence, and impact on the project.
Q8: What is a Work Breakdown Structure (WBS)? ANSWER A
hierarchical decomposition of the total scope of work to be carried out by the
project team.
Q9: What is the critical path? ANSWER The longest sequence of activities
in a project schedule that determines the minimum project duration.
Q10: What is scope creep? ANSWER The uncontrolled expansion of project
scope without adjustments to time, cost, and resources.
Q11: What is a milestone? ANSWER A significant point or event in a project
with zero duration that marks completion of a deliverable or phase.
Q12: What is the triple constraint? ANSWER The balance between scope,
time, and cost that defines project success.
,Q13: What is earned value management (EVM)? ANSWER A methodology
that combines scope, schedule, and resource measurements to assess project
performance.
Q14: What is a Gantt chart? ANSWER A bar chart that illustrates a project
schedule showing start and finish dates of project elements.
Q15: What is the difference between a risk and an issue? ANSWER A risk
is a potential future event that may impact the project; an issue is a current
problem requiring immediate attention.
Q16: What is resource leveling? ANSWER A technique to resolve resource
conflicts by adjusting start and finish dates based on resource constraints.
Q17: What is fast tracking? ANSWER A schedule compression technique
where activities normally done in sequence are performed in parallel.
Q18: What is crashing? ANSWER Adding resources to critical path activities
to reduce project duration.
Q19: What is a project baseline? ANSWER The approved version of scope,
schedule, and cost used as a reference for comparison.
Q20: What is change control? ANSWER A formal process to manage
changes to project documents, deliverables, or baselines.
Q21: What is a RACI matrix? ANSWER A responsibility assignment matrix
showing who is Responsible, Accountable, Consulted, and Informed for each
task.
Q22: What is quality assurance? ANSWER Process-oriented activities that
ensure the project will satisfy quality standards.
Q23: What is quality control? ANSWER Product-oriented activities that
verify deliverables meet quality requirements.
Q24: What is a risk register? ANSWER A document listing identified risks,
their probability, impact, and response strategies.
Q25: What is qualitative risk analysis? ANSWER Assessing risk probability
and impact using subjective scales to prioritize risks.
Q26: What is quantitative risk analysis? ANSWER Numerically analyzing
the effect of identified risks on project objectives.
Q27: What is a risk response strategy for threats? ANSWER Avoid,
Transfer, Mitigate, or Accept.
, Q28: What is a risk response strategy for opportunities? ANSWER Exploit,
Share, Enhance, or Accept.
Q29: What is procurement management? ANSWER The process of
purchasing or acquiring products, services, or results from outside the project
team.
Q30: What is a statement of work (SOW)? ANSWER A narrative
description of products, services, or results to be delivered by a vendor.
Q31: What is the difference between fixed-price and cost-reimbursable
contracts? ANSWER Fixed-price has a set price regardless of costs; cost-
reimbursable reimburses actual costs plus fee.
Q32: What is stakeholder engagement? ANSWER Activities to involve
stakeholders appropriately in project decisions and execution.
Q33: What is a communication plan? ANSWER A document defining who
needs what information, when, and through what channels.
Q34: What is scope validation? ANSWER The formal acceptance of
completed project deliverables by stakeholders.
Q35: What is a lessons learned register? ANSWER A document capturing
knowledge gained during the project for future reference.
Q36: What is project closure? ANSWER The final phase where project
activities are completed and formally closed.
Q37: What is float or slack? ANSWER The amount of time an activity can be
delayed without delaying the project.
Q38: What is the difference between leads and lags? ANSWER Leads allow
successor activities to start early; lags add waiting time between activities.
Q39: What is analogous estimating? ANSWER Using historical data from
similar projects to estimate duration or cost.
Q40: What is parametric estimating? ANSWER Using statistical
relationships between historical data and variables to calculate estimates.
Q41: What is bottom-up estimating? ANSWER Estimating work packages
individually and aggregating them to get total estimate.
Q42: What is three-point estimating? ANSWER Using optimistic,
pessimistic, and most likely estimates to calculate expected duration or cost.