You have a requirement to buy a large commercially available, prefabricated wash rack for your
installation. The catalog price is $102,000.
Simplified acquisition procedures can be used
The Director of training for the installation has a request to purchase 25 televisions and 25 DVD recorders
for the new training facility that will open next month. Each television will cost approximately $525, and
each DVD recorder about $150.
Simplified acquisition procedures can be used
You have a requirement for four military-unique fighter aircraft parts. Each part is estimated to cost 1.6
million.
Simplified acquisition procedures CANNOT be used.
You have a requirement to purchase equipment that was previously developed at Government expense
and sold exclusively to the military. This type of item is:
A non-developmental item
Evaluation factors are:
Stated in the solicitation
An oral solicitation may be used for:
Construction less than $2,000
The required sources of supplies and services can be found in:
FAR Part 8
You have a requirement for ship repair that will require a unique welding technique. You only know of a
few firms that have performed this technique and selecting an inexperienced contractor could be
disastrous. As such, you should primarily consider evaluating offerors':
Experience
When making a commercial purchase, you may conduct an in-process inspection:
At ay time to check that the product being made fits your specification
When no other exceptions apply, is a Government Point of Entry (GPE) synopsis required for purchases
estimated to exceed $25,000 but not to exceed the simplified acquisition threshold?
YES
Market research is performed
To determine if commercial or non-developmental items are available to satisfy agency needs