Verified Answers
Bidding documents are considered legal documents?
▪ True.
▪ False. Ans: False
Codes governing commercial construction and residential construction are different?
▪ True.
▪ False. Ans: True
The A/E usually hires a construction manager? Ans: False
The Owner, Contractor and A/E are parties to the construction agreement?
▪ True.
▪False. Ans: False
There are no differences between the AIA and EJCDC general conditions?
▪ True.
▪False. Ans: False
The drawings take precedence over the specifications?
▪ True.
▪False. Ans: False
,The role of a subcontractor is the same as a material supplier?
▪ True.
▪ False. Ans: False
The supplementary conditions should be coordinated with the Owner/A/E agreement?
▪ True.
▪Fals Ans: True
nProject descriptions and outline specifications are legal and binding documents?
▪ True.
▪False Ans: False
nThe contractor and the A/E review submittals for the same reasons and from the
same point of view?
▪ True.
▪False Ans: F
In 1964, the term "Project Manual" was introduced by the:
A. American Bar Association.
B. American Institute of Architects.
C. Construction Specifications Institute.
D. Department of Defense. Ans: B
© Get it right 2025 Getaway - Stuvia US All rights reserved
,Uniform Location of Subject Matterprepared by the EJCDC and jointly published by
EJCDC and AIA provides a recommended location of topics in all of the following
EXCEPT:
A. Supplementary Conditions.
B. Division 01.
C. Agreement.
D. Drawings. Ans: D
During the Planning/Pre-Design stage, the A/E may be retained to:
A. Develop outline specifications.
B. Describe the character of the mechanical system.
C. Prepare renderings.
D.Assist in financial feasibility studies Ans: D
During which project phase does the A/E review the Owner's program and budget
requirements and suggest alternative approaches?
A. Planning/Pre-Design.
B. Design.
C. Bidding/Negotiation.
D. Construction.
E. Post-Construction. Ans: B
© Get it right 2025 Getaway - Stuvia US All rights reserved
, A project's "life cycle" includes all of the following EXCEPT?
A. Planning/Design.
B. Financing.
C. Construction.
D. Evaluation.
E. Demolition. Ans: B
nThe Specification-type document prepared during the Design Development phase is
called the:
A. Outline Specification.
B. Rough Draft Specification.
C. UniFormat Elements. Ans: A
nThe contractual relationship governed by the Conditions of the Contract is between:
A. Owner and Contractor.
B. A/E and Contractor.
C. Owner and Subcontractors.
D.A/E and Subcontractors. Ans: A
nThe Agreement:
A. Establishes how the contract will be administered.