WITH CORRECT ANSWERS (VERIFIED)
1. A lump sum contract on a project has a total contract price of $160,000. Retainage
has been held back at 10%. The contractor has received progress payments for 75% of
the project. The contractor submits a request for final payment for the new completed
project. The final payment amount should be for...: More than $50,000
2. The owner requests for change which will cost the contractor $15,000 in labor and
materials and $2,250 in overhead costs. With the change, the contractor would be
relieved of $18,000 in labor and materials costs, and $2,400 in overhead costs from the
original contract. The original bid included profit of 20% of all costs. The contractor
wants to make a profit of 20% of all costs on the changes. The adjusted contract price for
the change order should be...: A decrease of $3,780
3. What is the total project overhead for a project that lasts 3 months and has the
following costs? Labor is $4,000; materials are $9,500; equipment rentals are $1,200;
superintendent's annual salary is $36,000; office rent is $800 per month; and office
utilities are $375 per month.: Less than $12,000
4. Which of the following would typically be covered by a contractor's comprehensive
general liability insurance policy?: Damage to adjoining property from a crane
accident
5. What is the total gross compensation and employment status for a carpenter, given the
following information? A contractor hires a carpenter to do the finish work for a 10-
home project. The carpenter is to be paid $16 per hour. The contractor provides all
materials and equipment, such as a table saw. The carpenter provides all of his own
hand tools. The contractor and the carpenter agree that all of the homes are to be
completed within 60 8-hour working days, without overtime. The contractor provides
the carpenter with a schedule of the order in which homes are to be worked on. The
contractor provides a helper to assist the carpenter. The contractor sets the work
schedule each day. The
carpenter spends 600 hours to complete this project, including 120 hours of overtime.:
The carpenter is an employee and is owed $10,560 for the project