CMP 101 Final Exam 2026 Questions and
Answers
As a construction manager for a road construction project, you would perform the
following tasks:
(Select all that apply)
- Hire skilled workers to perform the construction work
- Manage the finances to ensure the project makes profit.
- Operate all road building equipment
- Ensure the project is completed on time - Correct answer-- Hire skilled workers
to perform the construction work
- Manage the finances to ensure the project makes profit.
- Ensure the project is completed on time
For CMP101, what are the 2 types of construction?
- Building and Non-building construction
©COPYRIGHT 2025, ALL RIGHTS RESERVED 1
,- Residential and Commercial construction - Correct answer-Building and Non-
building construction
GC is an acronym for which one of the following?
- Generic Construction
- General Contractor
- Genoa City
- General Construction
- None of these - Correct answer-General Contractor
On a NON-RESIDENTIAL construction project, the Owner may directly hire the
following entities:
(SELECT ALL THAT APPLY)
- Electrical Engineer
- Architect
- Masonry Contractor
- Prime Contractor
- Construction Manager - Correct answer-- Architect
©COPYRIGHT 2025, ALL RIGHTS RESERVED 2
,- Construction Manager
On a residential construction project from the following construction activities,
what activity would be performed first
- Backfilling around foundation
- Installing Formwork for foundation
- Does not matter - Either one of these can be performed first.
- Pouring concrete for foundation
- Excavation for foundation - Correct answer-Excavation for foundation
Mechanical Plans are labeled in the title box as _______________ for the first
mechanical plan.
- None of these
- E1
- A1
- S1
- P1 - Correct answer-None of these
Which of the following discuss the quantity of work to be performed on a proposed
construction project?
©COPYRIGHT 2025, ALL RIGHTS RESERVED 3
, - Construction Plans/Drawings
- None of these
- Construction Specifications
- Construction Bid Form - Correct answer-Construction Plans/Drawings
Select the activities that must be completed prior to starting the sheetrock (drywall)
installation stage
- Mechanical, Electrical, and Plumbing (MEP) Rough-In
- Framing
- Insulation
- Interior Trims installation
- Interior Painting - Correct answer-- Mechanical, Electrical, and Plumbing (MEP)
Rough-In
- Framing
- Insulation
During the _______________________ the owner has occupied the new building,
but the contractor is still responsible to fix any issues arising due to poor
construction quality
©COPYRIGHT 2025, ALL RIGHTS RESERVED 4
Answers
As a construction manager for a road construction project, you would perform the
following tasks:
(Select all that apply)
- Hire skilled workers to perform the construction work
- Manage the finances to ensure the project makes profit.
- Operate all road building equipment
- Ensure the project is completed on time - Correct answer-- Hire skilled workers
to perform the construction work
- Manage the finances to ensure the project makes profit.
- Ensure the project is completed on time
For CMP101, what are the 2 types of construction?
- Building and Non-building construction
©COPYRIGHT 2025, ALL RIGHTS RESERVED 1
,- Residential and Commercial construction - Correct answer-Building and Non-
building construction
GC is an acronym for which one of the following?
- Generic Construction
- General Contractor
- Genoa City
- General Construction
- None of these - Correct answer-General Contractor
On a NON-RESIDENTIAL construction project, the Owner may directly hire the
following entities:
(SELECT ALL THAT APPLY)
- Electrical Engineer
- Architect
- Masonry Contractor
- Prime Contractor
- Construction Manager - Correct answer-- Architect
©COPYRIGHT 2025, ALL RIGHTS RESERVED 2
,- Construction Manager
On a residential construction project from the following construction activities,
what activity would be performed first
- Backfilling around foundation
- Installing Formwork for foundation
- Does not matter - Either one of these can be performed first.
- Pouring concrete for foundation
- Excavation for foundation - Correct answer-Excavation for foundation
Mechanical Plans are labeled in the title box as _______________ for the first
mechanical plan.
- None of these
- E1
- A1
- S1
- P1 - Correct answer-None of these
Which of the following discuss the quantity of work to be performed on a proposed
construction project?
©COPYRIGHT 2025, ALL RIGHTS RESERVED 3
, - Construction Plans/Drawings
- None of these
- Construction Specifications
- Construction Bid Form - Correct answer-Construction Plans/Drawings
Select the activities that must be completed prior to starting the sheetrock (drywall)
installation stage
- Mechanical, Electrical, and Plumbing (MEP) Rough-In
- Framing
- Insulation
- Interior Trims installation
- Interior Painting - Correct answer-- Mechanical, Electrical, and Plumbing (MEP)
Rough-In
- Framing
- Insulation
During the _______________________ the owner has occupied the new building,
but the contractor is still responsible to fix any issues arising due to poor
construction quality