Scheduling the Project

Purpose of a Schedule:
●​ Ensures the timely completion of a project
●​ Identifies what needs to get done and when
●​ Shows how all the pieces of the project fit together
●​ Team members see how their work affects others
●​ Used to monitor and control the project

Formats to create a Project Schedule:
●​ Gantt Charts
●​ Network Diagram
-​ PERT Network
-​ CPM Network


Network Diagrams
(Developed in the 1950s)
• Developed in the 1950’s
– A diagram of nodes and arrows (directional arcs)
– Illustrate the flow of activities
• Program Evaluation and Review Technique (PERT)
– U.S. Navy, Booz-Allen Hamilton, and Lockheed Aircraft
– Probabilistic activity durations (randomness)
– AOA
• Critical Path Method (CPM)
– Dupont De Nemours Inc.
– Deterministic activity durations (originally)
– AON


Event vs. Milestone
(0” duration – 0 hours or days)
Event
• An identifiable state
– Result of completing one or more activities
• Predecessor activities must be completed
Milestone
• Noteworthy event
• Marks significant progress

, Task Dependencies
(Precedence Diagram)
• Finish to Start
– Activity (predecessor) must finish before the successor can start.
– Dig hole – plant tree
• Start to Start
– Activity (predecessor) must start before the successor can start.
– Design code - code
• Finish to Finish
– Activity (predecessor) must finish before the successor can finish
– Test - documentation
• Start to Finish
– Activity (predecessor) must start before the successor can finish.
– Software cutover; new system implementation




An activity is an element of work that has:
– an expected duration
– a cost
– resource requirements
– predecessor
– successor
Sequencing Events (CPM)

, ●​ Path: A series of connected activities between two events (i.e. start/finish)
-​ Helps calculate Project Duration

Merge vs. Burst
Merge: An event which represents the joint completion of multiple activities.
Burst: An event which represents the beginning of multiple activities.



Critical Path

“Critical path”
-​ Series of activities (path) that determines the earliest time project can be completed
-​ Longest path through the network diagram
-​ Has the least amount of slack or float
What is Slack or Float?
-​ Amount of time an activity may be delayed without delaying project finish date
●​ Free – impacts successor
●​ Total – impacts total project

Critical Path Calculations
●​ First develop a good network diagram




●​ Add the duration estimates for all activities
●​ Calculated Early Start/Finish and Late Start/Finish/Slack
●​ The longest path is the critical path
-​ Activities have no slack
-​ If activities on the critical path slips, the whole project will be delayed
-​ Alerts PM to take corrective action

●​ Activities on all paths must be completed to finish the project
●​ The critical path is not the one with all the critical activities; it only accounts for time
●​ There can be more than one critical path if the lengths of two or more paths are the
same
●​ The critical path can change as the project progresses

Document information

Uploaded on
October 9, 2025
Number of pages
20
Written in
2025/2026
Type
Class notes
Professor(s)
Dr. kimberly marie deranek
Contains
All classes
$8.49
Get access to the full document:

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Get to know the seller
Seller avatar
megangray1

Also available in package deal

Thumbnail
Package deal
Project Management PIM 5455
-
8 2025
$ 67.92 More info

Get to know the seller

Seller avatar
megangray1 Nova Southeastern University
View profile
Follow You need to be logged in order to follow users or courses
Sold
-
Member since
5 months
Number of followers
0
Documents
8
Last sold
-

0.0

0 reviews

5
0
4
0
3
0
2
0
1
0

Trending documents

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions