Project - Answer an Interrelated set of activities with a definite starting and ending point,
which results in a unique outcome for a specific allocation of resources.
Project Management - Answer A systemized, phased approach to defining, organizing,
planning, monitoring and controlling projects.
Program - Answer An interdependent set of projects that have a common strategic purpose.
work breakdown structure (WBS) - Answer A statement of all work that has to be completed.
activity - Answer The smallest unit of work effort consuming both time and resources that the
project manager can schedule and control.
network diagram - Answer A network planning method, designed to depict the relationships
between activities, that consist of nodes (circles) and arcs (arrows).
program evaluation and review technique (PERT) - Answer A network planning method
created for the U.S. Navy's Polaris missile project in the 1950's, which involved 3,000 separate
contractors and suppliers.
Critical Path Method (CPM) - Answer A network planning method developed in the 1950's as a
means of scheduling maintenance shutdowns at chemical-processing plants.
precedence relationship - Answer A relationship that determines a sequence for undertaking
activities; it specifies that one activity cannot start until a preceding activity has been
completed.
Path - Answer The sequence of activities between a projects start and finish.
Critical Path - Answer The sequence of activities between projects start and finish that takes