CEPSCI EXAM WITH ALL CORRECT & 100% VERIFIED ANSWERS|LATEST UPDATE|ALREADY GRADED A+ (JUST RELEASED)

Rating
-
Sold
-
Pages
7
Grade
A+
Uploaded on
06-10-2025
Written in
2025/2026

CEPSCI EXAM WITH ALL CORRECT & 100% VERIFIED ANSWERS|LATEST UPDATE|ALREADY GRADED A+ (JUST RELEASED)

Institution
Certified Professional In Erosion And Sediment Control
Course
Certified Professional in Erosion and Sediment Control









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
Certified Professional in Erosion and Sediment Control
Course
Certified Professional in Erosion and Sediment Control

Document information

Uploaded on
October 6, 2025
Number of pages
7
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

CEPSCI EXAM WITH ALL CORRECT & 100% VERIFIED
ANSWERS|LATEST UPDATE|ALREADY GRADED A+ (JUST
RELEASED)
NPDES ✔Correct Answer-National Pollutant Discharge Elimination System

Clean Water Act ✔Correct Answer-Administered by the EPA in 1972

Water Quality Act ✔Correct Answer-Amendment to CWA in 1987 to regulate storm water
discharges under NPDES program

Point Source Pollution ✔Correct Answer-Discharges from readily identifiable sources like
treatment plants

Nonpoint Source Solution ✔Correct Answer-Runoff from urbanized or agricultural areas

NPDES in South Carolina ✔Correct Answer-SC is a delegated state. Regulations are administered by
SCDHEC

CGP Phase II ✔Correct Answer-Construction General Permit effective on September 1, 2006

NPDES Permit Coverage ✔Correct Answer-1 or more acres of land disturbance. Within 1/2 mile of
a receiving water body in SC Coastal Zone

NOI ✔Correct Answer-Notice Of Intent

CGP Requirements for OCRM ✔Correct Answer-Coverage granted 7 days after DHEC receives NOI

CGP Requirements for SCDOT ✔Correct Answer-Coverage granted 10 days after DHEC receives NOI

CGP Requirements for DHEC ✔Correct Answer-Coverage granted 20 days after DHEC receives
completed NOI

SWPPP ✔Correct Answer-Storm Water Pollution Prevention Plan, Completed prior to filing NOI,
Prepared in accordance with Phase II CGP

SWPPP Requirements ✔Correct Answer-Identification of operators
Sequence of construction
Locations of all BMP's
Locations of all surface waters of state

CGP Filing ✔Correct Answer-Must be in compliance with all other permits
Must comply with Federal reporting requirements
File NOT when construction is complete
Retain documentation 3 years.

Pre Construction meeting ✔Correct Answer-10 or more acres
Explain SWPPP to all co-permittees
Contractors that are not co-permittees and the preparer must be present

, Contractor Certification ✔Correct Answer-Co-permittees certify that are responsible for control of
the SWPPP and have participated in a Pre-Con meeting
All Contractors that are not co-permittees must certify accountability to DHEC and a Pre-Con meeting

EPSC Inspector Qualifications ✔Correct Answer-Individuals certified by a DHEC approved course.

Inspection Frequency ✔Correct Answer-(A) At least once every 7 days, or
(B) At least once every 14 days and within 24 hours of the end of a storm event of 0.5 inches or
greater
(C) Once a month if entire site is temporarily stabilized

Inspection Locations ✔Correct Answer-All areas disturbed by construction activities
Areas used for materials storage exposed to precipitation
Sediment/Erosion control structures in SWPPP
All discharge locations
Nearby downstream locations
Constuction entrances

Inspection Report ✔Correct Answer-1. Date
2. Inspector credentials
3. Weather info since last report
4. Description of any discharges occuring
5. locations of discharges of sediment or pollutants
6. Location of BMPs that need maintenance
7. Location of BMPs that have failed
8. Location of additional BMPs needed
9. Corrective actions required

Notice Of Termination ✔Correct Answer-Can be submitted if one of the following conditions have
been met:
1. Final stabilization has been achieved on all portions of site
2. Another operator has assumed control
3. Residential temporary stabilization in place and deed has been transferred to new owner

Stop Work Order ✔Correct Answer-Can be issued if:
Off site sedimentation resulting from non compliance
Work is being conducted without an approved SWPPP

Potential Enforcement Actions ✔Correct Answer-Civil penalty of $1000 a day of violation
Violation of SC Pollution Control Act:
Misdemeanor and fines not less than 500 or more than $25000 for each days violation
Civil penalties not to exceed $10000 per day

Runoff Control BMPs ✔Correct Answer-Pipe slope drain
Runoff diversion measures
Temporary stream crossing
Construction de-watering

Pipe Slope Drain ✔Correct Answer-PSDs are for water to flow down slope without causing erosion
especially before slope has been stabilized or used before permanant drainage structure are installed

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Studyclub Yale School Of Medicine
View profile
Follow You need to be logged in order to follow users or courses
Sold
24
Member since
1 year
Number of followers
0
Documents
8846
Last sold
2 days ago
"The Club for Top Academic Performance."

Welcome to StudyClub—the ultimate destination for students who want to make studying not only effective but also enjoyable! Whether you’re preparing for an exam, looking to improve your grades, or mastering new subjects, StudyClub is your go-to space to find the tools and resources you need to succeed. At StudyClub, I believe in the power of community. That’s why I’ve created a collection of high-quality study materials designed to simplify complex concepts and help you achieve your academic goals. Whether you’re an individual looking to study independently or a student seeking the support of a virtual study group, you’ll find everything you need to succeed. Join the StudyClub today, where learning is made easier, more organized, and—most importantly—more collaborative. Let’s grow together, learn smarter, and unlock your academic potential. Thank you for being part of the StudyClub community. I can’t wait to see you succeed!

Read more Read less
3.6

7 reviews

5
4
4
0
3
1
2
0
1
2

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions