A responsibility assignment matrix (RAM) allows the project manager to cross reference: a. the work breakdown structure (WBS) with the organisational breakdown structure (OBS) to match resources to the tasks. b. the organisational breakdown structure (OBS) with the cost breakdown structure (CBS) to assign a cost to each resource. c. the product breakdown structure (PBS) with the work breakdown structure (WBS) to assign activities to the products. d. the organisational breakdown structure (OBS) with the product breakdown structure (PBS) to assign resources to deliverables. - ANSWER-A Which one of the following is a valid description of the phases of a complete project lifecycle? a. Start-up, feasibility, planning, execution and roll-out. b. Concept, screening, implementation, handover and closeout. c. Concept, definition, implementation, handover and closeout. d. Start-up, definition, development and production closedown. - ANSWER-C Which one of the following best describes project management? a. Using APM's Body of Knowledge 6th edition as a guide to all projects. b. Employing a project manager who has undertaken similar projects. c. Utilising team members who can work on a project full time. d. Application of processes and methods throughout the project life cycle. - ANSWER-D

Show more Read less
Institution
UPDATED APM PFQ
Course
UPDATED APM PFQ

Content preview

UPDATED APM PFQ EXAM 2025 TEST BANK 400+ QUESTIONS
AND CORRECT ANSWERS (PROFESSOR VERIFIED AND JUST
RELEASED)


A responsibility assignment matrix (RAM) allows the project
manager to cross reference:
a. the work breakdown structure (WBS) with the organisational
breakdown structure (OBS) to match resources to the tasks.
b. the organisational breakdown structure (OBS) with the cost
breakdown structure (CBS) to assign a cost to each resource.
c. the product breakdown structure (PBS) with the work breakdown
structure (WBS) to assign activities to the products.
d. the organisational breakdown structure (OBS) with the product
breakdown structure (PBS) to assign resources to deliverables. -
ANSWER-A


Which one of the following is a valid description of the phases of a
complete project lifecycle?
a. Start-up, feasibility, planning, execution and roll-out.
b. Concept, screening, implementation, handover and closeout.
c. Concept, definition, implementation, handover and closeout.
d. Start-up, definition, development and production closedown. -
ANSWER-C


Which one of the following best describes project management?
a. Using APM's Body of Knowledge 6th edition as a guide to all
projects.
b. Employing a project manager who has undertaken similar
projects.

,c. Utilising team members who can work on a project full time.
d. Application of processes and methods throughout the project life
cycle. - ANSWER-D


Which structure shows the reporting relationships and
communications channels for a project?
a. Work Breakdown Structure.
b. Organisational Breakdown Structure.
c. Product Breakdown Structure.
d. Responsibility assignment structure. - ANSWER-B


Key performance indicators (KPIs) are used for measuring how a
project is progressing towards success and are monitored by project
managers:
a. at the post-project review.
b. not more frequently than monthly.
c. throughout the project.
d. only when assessing project risk. - ANSWER-C


Which one of the following best characterises a project?
a. An ongoing activity to maintain the company plant.
b. A transient endeavour carried out to meet specific objectives.
c. Continuous improvement of the company procedures.
d. Manufacturing components for a new technology. - ANSWER-B


What is meant by the term programme management?

,a. The management of a group of projects or activities that have a
common business aim.
b. The line management of a team of programme managers.
c. The management of a functional area used by a number of
different projects.
d. The management of the programme of activities identified in the
project plan - ANSWER-A


The main purpose of configuration management is to:
a. minimise the impact of changes on the scope of the project.
b. ensure that the final product meets the strategic needs of the
business.
c. provide control of the deliverables and avoid mistakes or
misunderstandings.
d. maximise the impact of agreed enhancements on the project
deliverables. - ANSWER-C


The accuracy of an estimate should:
a. decrease as a project progresses through its lifecycle.
b. increase as a project progresses through its lifecycle.
c. stay constant throughout the project.
d. vary independently of where the project is in its lifecycle -
ANSWER-B


What would be the effect if the resources required for a project's
critical path activities were insufficient?
a. It would reduce the project duration.
b. It would extend the project duration.

, c. The quality of the deliverables would suffer.
d. Resource smoothing should be applied to the critical path. -
ANSWER-B


Which one of the following is the best description of project scope?
a. Scope is detailed in the business case.
b. Scope is the total work content of a project.
c. Scope is an outcome of the scheduling and estimating processes.
d. Scope defines what is NOT delivered by the project. - ANSWER-B


When delivering a project the Project Manager has to balance which
one of the following constraints:
a. definition and delivery.
b. time, cost and quality.
c. cost and scope.
d. budget, spend and contingency - ANSWER-B


Which one of the following statements is true?
a. Business-as-usual activities cannot be improved.
b. Business-as-usual activities are more difficult to manage than
projects.
c. Projects are transient endeavours that bring about change to
business-as-usual.
d. A project is always the starting point for operational refinement. -
ANSWER-C


What is the purpose of a stakeholder grid?

Written for

Institution
UPDATED APM PFQ
Course
UPDATED APM PFQ

Document information

Uploaded on
October 3, 2025
Number of pages
101
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

$17.99
Get access to the full document:

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
docciel Walden University
View profile
Follow You need to be logged in order to follow users or courses
Sold
23
Member since
3 year
Number of followers
11
Documents
1116
Last sold
4 days ago

5.0

3 reviews

5
3
4
0
3
0
2
0
1
0

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions