something completed once, unique situation
Project -unique output with desired outcome, limited budget,
deadline
1) Define the project
2)Establish Project Priorities
Project Management (4 steps)
3)Work Breakdown Structure
4) Track project progress
Define the project objectives and deliverables
Establish project priorities cost, time, performance
create AON diagram, break down work into smallest units
1) people - who is the accountable party, who else is
Work breakdown structure involved
2)time - estimate
3)cost- estimate
Track project progress use AON diagram
3 points- cost, time, performance
Project priorities triangle center- quality
* all about trade offs
Goals, measurable, expectations or desired outcomes of
Objectives
budget, time, performance, and auality
description of services/ products to be delivered:
Deliverables Presentation and or documents, research, physical item or
intangible outputs
a specific event in a project: date of an important decision,
Milestones
start or end of phase, deadline
Activity on node - network diagrams that use nodes to
AON Diagram designate activities; nodes represent the beginning and
end points of activities and are also referred to as events
, critical path 1/7