QUESTIONS AND CORRECT
ANSWERS
"Perhaps the most important item considered at the estimate review is ____. - Correct
Answer the amount of fee to include in the bid price"
"While an experienced estimator will certainly know what to look for and assess when
investigating the site, the presence of the ____ or a project superintendent on the visit will
always be valuable if only to offer alternative viewpoints in the evaluation of the data
obtained. - Correct Answer chief estimator"
"An estimate begins with a quantity takeoff. - Correct Answer True"
"The estimator should note that quantities of materials are measured in the takeoff process. -
Correct Answer False"
"A materials takeoff generally provides sufficient information for pricing. - Correct Answer
False"
"There are four basic categories of units used in estimating: number, length, area, and weight.
- Correct Answer False"
We put together estimates all the time in our everyday lives, often with little or no
calculating. - Correct Answer True"
"The different project delivery systems use the same types of estimates— conceptual,
preliminary and detailed—at various stages in the development of the project. - Correct
Answer False"
"With the design- build method, the owner indicates that he or she requires a certain facility
and usually outlines some parameters relating to location, size, design and the desired time
of occupancy. - Correct Answer True"
,"Most general contractors and subtrades enter into cost-plus contracts in order to perform a
defined scope of work. - Correct Answer False"
"A(n) ____ in its essence is an assessment of the probable total cost of some future activity. -
Correct Answer estimate"
"A ____ estimate has to be prepared from a minimum amount of information because it is
required at a time when the project is often little more than a vague idea in the mind of the
owner. - Correct Answer conceptual"
"Once the design of a project is underway, budget amounts can be established for the
various elements of the project using procedures for a ____ estimate. - Correct Answer
preliminary"
"Using a construction management organization seeks to facilitate overlap between project
stages, often referred to as ____, to allow earlier completion of the project. - Correct Answer
fast tracking"
"____ contracts are usually the owner's choice of last resort because they can place the
owner in a vulnerable financial position. - Correct Answer Cost-plus"
"____ contracts are based on a pricing schedule that consists of a breakdown of the work
and estimated quantities for each of the items on the breakdown. - Correct Answer Unit-
price"
"The basis of a ____ is the accurate assessment of the work in the form of a quantity takeoff
that can only be obtained from the full design of the project - Correct Answer detailed
estimate"
"Construction groups in major cities have formed associations or plan service centers where
both public and private bodies may deposit plans and specifications of projects calling for
bids. - Correct Answer True"
"In a closed bid system the number of companies invited to bid is typically limited to no more
than ten contractors who are known to the owner or designers and who meet the
qualification criteria set by the owner. - Correct Answer False"
"An effective way to proceed with the planning of estimating operations is achieved by
means of a simple line chart form of time schedule. - Correct Answer False"
"On most projects general contractors request two complete sets of bid documents for
estimating a project. - Correct Answer True"
, "If an estimator does not know exactly what the computer is accomplishing in the
preparation of an estimate, the estimator will not be in control of the process. - Correct
Answer True"
"The use of fax machines, cellular telephones, and e-mail has had little impact on the bidding
process as it is still mostly a manual process. - Correct Answer False"
"Agencies of the U.S. government use a standard form called the "____" to provide bid
information. - Correct Answer Pre-Solicitation Notice"
"Private owners often directly invite contractors to bid on their construction projects in a
system known as a(n) ____ system. - Correct Answer Closed bid"
"A method of addressing the problem of bids from contractors of questionable financial
situation and experience capability is to call for bids only from ____ contractors. - Correct
Answer prequalified"
"Designers usually require a cash or certified check deposit from contractors who obtain bid
documents and the deposit is reimbursed when the drawings and specifications are returned
to the designer's office in "____." - Correct Answer Good order"
"A method of handling the problem of review questions is to compile a list of all the
questions that arise, the ____, then later make a single call to the designer to cover all the
items that have accumulated. - Correct Answer query list"
"Significant details provided in response to questions about a bid will be incorporated into
written documents that are distributed to all bidders in publications that are known as ____. -
Correct Answer addenda"
"A perimeter length is calculated from the figured dimensions that are provided on the plan
of the structure. - Correct Answer True"
"A ____ is a process of measuring the work of the project in the form of a series of quantified
work items. - Correct Answer quantity takeoff"
"In a quantity takeoff, measurements are made ____. - Correct Answer net in place"
"Dimensions are entered onto the takeoff in this order: ____. - Correct Answer length, width,
and depth"