Quiz_________________?
What is minimum power for X50R2? 90/110/120 -
Answer✅
90 min, 100-240 recommended
Quiz_________________?
What arrays require high-line (208-40 VAC) power?
A. X10, X20
B. X50, X50R2
C. X50R3, X70, X90 -
Answer✅
B
Quiz_________________?
When do you need to swap out power supplies?A. X50 -> X70B. X50R2 -> X50R3C. X10 -
> X50 -
Answer✅
B. The //X50R3 must run on high-line power (180 - 264 V). Unlike previous generations of
//X50, it cannot use 120 VAC.
1
, Quiz_________________?
What is proper way to cycle power for an array?A. Pull power cords from shelves, then
power cords from controllersB. Unplug cable from PSU0 (CT0), then uplug cable from
PSU1 (CT1), then unplug power from shelvesC. Unplug cables from PDUs for the
controllers first and then from shelves -
Answer✅
B. Unplug power cables from chassis (wait 10 seconds) before unplugging from shelves. Do
not disconnect cables from PDUs.Powering Off a FlashArray//XR2 or //XR3 or DirectFlash
ShelfTo power off a FlashArray//XR2 or //XR3 or DirectFlash shelf, essentially all you do is
disconnect the power cords. Perform these steps:1. Unwrap the captive strap from each
power plug. 2. Remove power plug from PSU socket 0.3. Remove power plug from PSU
socket 1.You are not required to shut Purity down or switch a controller off before
removing the power plug.
Quiz_________________?
Which //X models support 120V? -
Answer✅
X10 & X20
Quiz_________________?
What is required voltage for X50, X70, X90? -
Answer✅
X50R2 can run on 120VAC. X50R3, X70(R2/R3) & X90(R2/R3) require 240V
Quiz_________________?
You order multiple arrays - how many are supported with Activecluster? Options:a. 2b. 3c.
4d. 6 -
Answer✅
A
Quiz_________________?
ActiveCluster IP replication- how many management IPs are required? -
2
, Answer✅
5 management IP addresses are required -- 3 will be assigned to vir0, ct0.eth0, ct1.eth0 and
2 will be assigned to eth1 management ports ct0.eth1 and ct1.eth1. Assigning IP address to
vir1 interface is optional. If vir1 is configured (optional) then, 6 total IP addresses are
required
Quiz_________________?
Upgrade M50R2 to X70R3 with a SAS shelf. What do you need? A. SAS-Ethernet cables B.
Pair of SAS cards C. Ethernet cables -
Answer✅
B. Pair of SAS cards.
Quiz_________________?
Command to make sure both controllers are online and in a ready state
A - pureadm status
B - pureadmin status
C - pureadm status --controllers -
Answer✅
A - pureadm status
Quiz_________________?
Command to set hardware upgrade tag for alerts?
A - purealert tag --timeout 240m --maintenance
B - purealert --tag --timeout 240m --maintenance
C - purealert tagging --timeout 240 maintenance -
Answer✅
A: purealert tag --timeout 240m --maintenance ---OR---- purealert tag --timeout 240m --
puremaintenance
Quiz_________________?
3
, When do you replace power supplies for an upgrade?
A - before replacing the controllers
B - after replacing the controllers
C - after shutdown -
Answer✅
A - Before replacing the controllers
Quiz_________________?
Command to check power supply status?
A - purehw list type power
B - purehw --list type pwr
C - purehw list --type pwr -
Answer✅
C - purehw list --type pwr
Quiz_________________?
Command to monitor status of phonehome command?
A - purearray -phonehome --status
B - purearray phonehome --status
C - purearray phonehome status -
Answer✅
B - purearray phonehome --status
Quiz_________________?
Command to check the contoller I/O? (Pre-4.1.4)
A - iobalance --sampletime 30
B - iobalance sampletime -30
C - iobalance -sampletime --30 -
4