Purpose Statement: DBIA is the only organization that _____ , _____, and _____
best practices in design-build project delivery.
- defines
- teaches
- promotes
_____ _____ is the belief that there is a technique, method or process that is more
effective at delivering a particular outcome than any other.
Best practice
With proper ____, ____, and ____ a desired outcome can be delivered with fewer
problems and unforeseen complications.
- process
- checks
- testing
Implementing the best practices on any type of DB project _____ the probability
of a _____ project that meets the expectations of all _____.
- increases
- successful
- stakeholders
What are the 5 types of project delivery systems?
- DB
- DBB
- CMAR
- IPD
- Multiple prime contracting
What are the 5 Owner's objectives?
- Control
- relationships
- project budget
- project schedule
- risks
_____ is a linear sequential process.
DBB
In DBB, the A/E is typically selected on _____ and the GC is typically selected on
_____ _____.
,- qualifications
- low price
In DBB, design is fully completed _____ input from the GC.
Without
In DBB, the Owner has a "_____ of _____ relationship" with the A/E.
Standard of Care Relationship
In DBB, the Owner has a "_____ relationship" with the Contractor.
Spearing Relationship
What 2 methods of selection (procurement methods) does CMAR use?
- QBS
- Best Value
Who provides the pre-construction services for CMAR?
Contractor
What kind of contracting approach is usually used in CMAR?
Negotiated GMP
What is special about the estimating process in CMAR?
it is an open-book
Which delivery methods have the chance to fast track the schedule?
- DB
- CMAR
What is one characteristic of the scope in 3rd party assistance?
The scope of services varies widely
Using a 3rd party professional does NOT constitute a new _____ _____.
delivery system
Delivery systems alone, do not predict _____
Success
Owners drive project success by strategically selecting strategies that promote
team _____ and group _____.
- integration
- cohesion
In CMAR, the construction cost is determined _____ the design is completed.
Before
, In CMAR, the Owner procures and manages designers and contractors under
(one / two separate) contracts?
two separates
In CMAR, the _____ negotiates the full commercial deal.
Owner
In CMAR, what is the direct contractual relationship between the contractor and
designer?
There is no direct contractual relationship
In CMAR, there is _____ public sector authority for its use.
Limited
In _____, the owner contracts with one single entity for both design and
construction.
DB
In which project delivery method do the designer and contractor have a direct
contractual relationship?
DB
Which project delivery method has multiple organizational structures?
DB
In DB, how is the Design-Builder generally selected?
QBS or Best Value
Which delivery methods generally uses the selection process of QBS and Best
Value?
- DB
- CMAR
Which delivery method has a wide spectrum of contracting approaches?
DB
The DB system has a(n) _____ _____ of responsibility.
Single Point
In DB, the Owner (does / does not) manage the designer.
Does NOT
What creates innovation potential in DB?
Collaboration between the Owner, Contractor, and Designer
Which delivery method gives early knowledge of the project cost?