APM- PFQ EXAM LATEST 2024 ACTUAL EXAM TEST BANK 420 QUESTIONS AND CORRECT DETAILED
ANSWERS

Which of the following is not a stage in an issue resolution process?

a. Share the issue with stakeholders.

b. Track the issue to closure. c. Escalate to the sponsor.

d. Apply change control. - (answer) A



Which of the following are challenges for a project manager developing and leading a project team?

1) Issues and incompatibility amongst team members

2) Getting the right skills and attributes amongst team members

3) Co-location of team members in the same geographic area

4) Lack of accountability of team members

a. 1, 2 & 3

b. 1, 2 & 4

c. 1, 3 & 4

d. 2, 3 & 4 - (answer) C



Which of the following is an activity in a typical change control process?

a. Recommendation.

b. Justification.

c. Planning.

d. Continuous improvement - (answer) A



The purpose of quality assurance is to:

a. provide confidence the project will satisfy the relevant quality standards.

b. determine a set of procedures and standards for project management.

c. inspect, measure and test deliverables and processes.

d. define the scope and specifics of a project's deliverables - (answer) A



A project manager might use a PESTLE analysis in order to:

,APM- PFQ EXAM LATEST 2024 ACTUAL EXAM TEST BANK 420 QUESTIONS AND CORRECT DETAILED
ANSWERS

a. mitigate all possible risks to the project.

b. identify and mitigate factors that may affect the project.

c. control technological change during the project.

d. consider team social roles in early stages of the project - (answer) B



Which of the following are phases in an iterative project life cycle? 1) Concept 2) Feasibility 3)
Deployment 4) Development

a. 3 and 4 only

b. 1, 2 and 3

c. 1 and 2 only

d. 2, 3 and 4 - (answer) D



Which of the following is the responsibility of a project manager?

a. Ensuring a project is aligned to the organisation's strategy.

b. Focusing on project benefits and aligning priorities.

c. Achieving the project's success criteria.

d. Improving process, tools and techniques used in a project - (answer) C



To develop and establish a proper communication plan within a project, the project manager needs to
consider which type of analysis?

a. Budget.

b. Stakeholder.

c. Resource.

d. Schedule - (answer) B



Which of the following is a responsibility of the project sponsor?

a. Creating a project cost breakdown structure.

b. Authoring the project management plan.

c. Creating a project work breakdown structure.

,APM- PFQ EXAM LATEST 2024 ACTUAL EXAM TEST BANK 420 QUESTIONS AND CORRECT DETAILED
ANSWERS

d. Owning the project business case. - (answer) D



Portfolio management includes prioritising:

a. projects and/or programmes that contribute directly to the organisation's strategic objectives.

b. projects with exceptionally high returns on investment.

c. projects and programmes over business as usual.

d. projects which maximise change over those which maximise investment - (answer) A



Which of the following actions would not help a team leader influence the performance of their team?

a. Creating an exclusive environment.

b. Providing clear roles and responsibilities.

c. Promoting openness and honesty.

d. Developing a trusting relationship. - (answer) A



One difference between a project and business as usual is:

a. projects achieve specified benefits but business as usual has only vague benefits.

b. projects drive change whereas business as usual continues existing activities.

c. projects have tightly controlled budgets whereas business as usual does not.

d. projects have unclear deadlines but business as usual has multiple milestones - (answer) B



The purpose of project progress reporting is to:

a. ensure a simpler critical path.

b. enable the tracking of project deliverables.

c. ensure stakeholder acceptance of project deliverables.

d. provide an increased total float. - (answer) B



Which of the following is the purpose of an estimating funnel?

a. Keeping resource usage to a minimum to help reduce costs.

, APM- PFQ EXAM LATEST 2024 ACTUAL EXAM TEST BANK 420 QUESTIONS AND CORRECT DETAILED
ANSWERS

b. Supporting the production of comparative estimates.

c. Identifying where costs can be minimised when preparing a budget.

d. Representing increasing levels of estimating accuracy achieved through the life cycle - (answer) D



One advantage of virtual communications is:

a. that nonverbal signals can have an impact on discussions.

b. it's easy to detect signs of conflict within the project team.

c. access to a wider resource pool for the project.

d. that the project team will always be co-located. - (answer) C



Which technique could be used by a project manager when resources are limited?

a. Resource aggregation.

b. Resource estimation.

c. Resource levelling.

d. Resource expansion - (answer) C



The main aim of quality management is to:

a. prepare a high-quality management plan.

b. ensure that deliverables meet appropriate standards.

c. validate the use of consistent standards.

d. determine whether to accept change requests. - (answer) B



Which of the following is a purpose of issue management?

a. To stop issues occurring within the project.

b. To address and resolve the issues that occur.

c. To address and resolve uncertainty.

d. To reschedule activities to reduce costs - (answer) B

Document information

Uploaded on
September 10, 2025
Number of pages
77
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$17.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Testmister
5.0
(515)
Sold
2689
Followers
2
Items
1189
Last sold
6 hours ago


Reviews from verified buyers



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions