MQM Exam 2 Questions and Answers Already Passed Latest Update The job of the project manager is to: A. Control all costs B. Control costs, schedule, and performance of the project C. Keep within the budget, no matter what D. All of the above - Answers B. Control costs, schedule, and performance of the project The purpose of performing a forward pass is to: A. Identify the critical path B. Determine the early start and the early finish times C. Determine the late start and the late finish times D. Determine the slack available in the process - Answers B. Determine the early start and the early finish times An assumption of the PERT method is: A. Activity times are not constant. B. There is uncertainty in individual activity time estimates. C. Distribution of project completion times and the probability that each activity is on the critical path can be computed. D. All of the above - Answers D. All of the above Project management requires: A. Scheduling, planning, and controlling B. Quantitative skills C. Behavioral skills D. All of the above - Answers D. All of the above Multiple critical paths can exist under the critical path method (CPM) because: A. There is more than one way to complete the project B. Different network paths can have the same total time C. Great flexibility of activity sequences is available D. None of the above - Answers B. Different network paths can have the same total time Gantt charts are effective for project scheduling if: A. Activities are highly interconnected B. Activity times are random C. The project contains simple activity sequences D. All of the above - Answers C. The project contains simple activity sequences Controlling a project does NOT include: A. Monitoring costs, time, and performance B. Adhering to the budget C. Correcting the plan as necessary D. None of the above - Answers D. None of the above Which of the following statements is true about a critical path? A. It consists of activities for which early start time equals late start time.

Content preview

MQM Exam 2 Questions and Answers Already Passed Latest Update 2025-2026

The job of the project manager is to:



A. Control all costs

B. Control costs, schedule, and performance of the project

C. Keep within the budget, no matter what

D. All of the above - Answers B. Control costs, schedule, and performance of the project

The purpose of performing a forward pass is to:



A. Identify the critical path

B. Determine the early start and the early finish times

C. Determine the late start and the late finish times

D. Determine the slack available in the process - Answers B. Determine the early start and the
early finish times

An assumption of the PERT method is:



A. Activity times are not constant.

B. There is uncertainty in individual activity time estimates.

C. Distribution of project completion times and the probability that each activity is on the critical
path can be computed.

D. All of the above - Answers D. All of the above

Project management requires:



A. Scheduling, planning, and controlling



B. Quantitative skills

,C. Behavioral skills



D. All of the above - Answers D. All of the above

Multiple critical paths can exist under the critical path method (CPM) because:



A. There is more than one way to complete the project

B. Different network paths can have the same total time

C. Great flexibility of activity sequences is available

D. None of the above - Answers B. Different network paths can have the same total time

Gantt charts are effective for project scheduling if:



A. Activities are highly interconnected

B. Activity times are random

C. The project contains simple activity sequences

D. All of the above - Answers C. The project contains simple activity sequences

Controlling a project does NOT include:



A. Monitoring costs, time, and performance

B. Adhering to the budget

C. Correcting the plan as necessary

D. None of the above - Answers D. None of the above

Which of the following statements is true about a critical path?



A. It consists of activities for which early start time equals late start time.

, B. The total time of activities on the path take the longest time.

C. There is no slack in the activities along the critical path.

D. All of the above. - Answers D. All of the above.

Project managers' objectives include:



A. Cost

B. Quality

C. Flexibility

D. All of the above - Answers A. Cost

Project managers' work includes:



A. Planning, Scheduling, Control, and Closing

B. Planning, Scheduling, Starting, and Ending

C. Scheduling, Control, Starting, and Ending

D. None of the above - Answers A. Planning, Scheduling, Control, and Closing.

The advantage(s) of the network method over the Gantt chart is (are) that:



A. The network method is easy to use and quite widely understood.

B. The network method shows precedence relationships more explicitly than Gantt charts.

C. Network methods are less costly to use.

D. All of the above - Answers B. The network method shows precedence relationships more
explicitly than Gantt charts.

The advantage(s) that the Gantt chart has over the network method is (are):



A. A Gantt chart is easy to use and quite widely understood.

B. Gantt charts show precedence relationships more explicitly than network scheduling.

Document information

Uploaded on
September 8, 2025
Number of pages
17
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$10.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
TutorJosh
3.4
(74)
Sold
476
Followers
16
Items
32589
Last sold
7 hours ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions