A Subcontractor's employee incorrectly performs the Work. Who is
responsible (to the Owner) for the error?
1- Subcontractor employee
2- Architect
3- Subcontractor
4- Contractor - ANSWER -A201: 3.3.2
Article 3) Contractor
3.3 Supervision and Construction Procedures
4- Contractor
Which of the following is NOT a cause for the Owner to terminate the
Contract?
1- The Contractor experiences delays due to a Stop Work order through
an act of government
pg. 1
,2
2- The Contractor fails to make payment to Subcontractors for labor
3- The Contractor is guilty of substantial breach of a provision of the
Contract Documents
4- The Contractor repeatedly fails to supply enough properly skilled
workers - ANSWER -A201: 14.2.1
Article 14) Termination or Suspension of the Contract
14.2 Termination by the Owner for Cause
1- The Contractor experiences delays due to a Stop Work order through
an act of government
Which of the following is owner of all drawings and specifications?
1- Contractor
2- Owner
3- Architect
4- Supplier - ANSWER -A201: 1.5.1
Article 1) General Provisions
pg. 2
,3
1.5 Ownership and Use of Drawings, Specifications and Other
Instruments of Service
3- Architect
Except for those Claims excluded by this AIA A201 Section 15,2,1, an
initial decision shall be required as a condition precedent to mediation
of any Claim arising prior to the date final payment is due, unless 30
days have passed after the Claim has been referred to the Initial
Decision Maker with no decision having been rendered.
1- 10
2- 20
3- 15
4- 30 - ANSWER -A201: 15.2.1
Article 15) Claims and Disputes
15.2 Initial Decision
pg. 3
, 4
4- 30
The ____________ will on request furnish to a ____________
information regarding percentages of completion or amounts applied
for by the Contractor
1- Subcontractor; Owner
2- Architect; Subcontractor
3- Owner; Subcontractor
4- Owner; Architect - ANSWER -A201: 9.6.3
Article 9) Payments and Completiong
9.6 Progress Payments
2- Architect; Subcontractor]
To whom is the Subcontractor bound to by the Contract Documents?