Perfectly 100%.
Incorrect heat input control when welding stainless steels can result in:
A) lack of diffusion.
B) heat tinting.
C) increased penetration.
D) decreased penetration. correct answers B
Three key items for the welding inspector to verify before welding are:
A) correct design drawing, correct standards, and correct materials.
B) approved technical standards, correct materials, and correct standards.
C) correct materials, qualified welders, and approved welding procedures.
D) condition of equipment, adequate supply of electrodes, and qualified welders.
E) alternate electrodes, safety equipment, and approved welding procedures. correct answers C
During post weld heat treatment an inspector may be required to monitor certain items. This
could include:
A) heating and cooling rates.
B) minimum temperature difference between thermocouples.
C) calibrations of the torch assemblies used.
D) confirmation of mechanical temperature results. correct answers A
During welding, the inspector may be called upon to check:
A) that Post Weld Heat Treatment has been completed.
B) that the welding parameters conform to the approved procedures.
C) the completion of the Inspection Test Plan (ITP).
, D) that all weldments have been completed. correct answers B
When non-destructive examination such as UT is specified, is visual inspection still required?
A) Only if detailed in the contract
B) Only upon request of the fabricator
C) Yes, visual inspection should be included
D) Not for any pressure equipment correct answers C
ASME Section VIII does not oversee the qualification of welding consumables. (True/False)
correct answers TRUE
What does soaking refer to?
A) The cooling rate after heat treatment
B) The temperature holding time during PWHT
C) A form of quenching
D) The post weld cleaning process correct answers B
What action should be taken in the event of a nonconformance?
A) The design engineer will be informed immediately.
B) There will be procedures for dispositioning a nonconformance.
C) The part will be repaired before a nonconformance is reported.
D) The part will be scrapped before a nonconformance is generated.
E) The inspector will contact the client immediately. correct answers B
What is the function of interim inspection reports?
A) They are of little value as a means of quality control
B) To provide engineering and production personnel with information of which they might not
otherwise be aware.