The stormwater Notice of Intent (NOI) must be submitted - CORRECT ANSWERS After
the SWPPP is prepared and before starting construction
Potential pollutant sources stored on a construction site may include - CORRECT
ANSWERS Petroleum storage tanks, soil amendments, masonry materials -- all of the above
The SWPPP implementation sequence may be modified - CORRECT ANSWERS After
consulting with the project SWPPP designer (CEC) and if required the Project Engineer
A SWPPP Site Map will show all of the following except - CORRECT ANSWERS Notices of
Violation
Which of the following information is to be posted at the entrance to the site? - CORRECT
ANSWERS Construction Site Notice, Permit authorization, Location of the SWPPP -- All of
the above
The 1970's law that set into place the regulation of stormwater is: - CORRECT ANSWERS
The Clean Water Act
Requirements for managing stormwater activity on a construction site are outlined in the
following regulation: - CORRECT ANSWERS NPDES
Which of the following is never an allowable stormwater discharge from a construction site? -
CORRECT ANSWERS Discharge from contaminated groundwater
The Notice of termination can filed when: - CORRECT ANSWERS All construction
activity, inside and outside the building, is complete and permanent stabilization verified
UPDATED 2025/2026 ALL ANSWERS CORRECT VERIFIED RATED
A+ FOR SUCCESS
The stormwater Notice of Intent (NOI) must be submitted - CORRECT ANSWERS After
the SWPPP is prepared and before starting construction
Potential pollutant sources stored on a construction site may include - CORRECT
ANSWERS Petroleum storage tanks, soil amendments, masonry materials -- all of the above
The SWPPP implementation sequence may be modified - CORRECT ANSWERS After
consulting with the project SWPPP designer (CEC) and if required the Project Engineer
A SWPPP Site Map will show all of the following except - CORRECT ANSWERS Notices of
Violation
Which of the following information is to be posted at the entrance to the site? - CORRECT
ANSWERS Construction Site Notice, Permit authorization, Location of the SWPPP -- All of
the above
The 1970's law that set into place the regulation of stormwater is: - CORRECT ANSWERS
The Clean Water Act
Requirements for managing stormwater activity on a construction site are outlined in the
following regulation: - CORRECT ANSWERS NPDES
Which of the following is never an allowable stormwater discharge from a construction site? -
CORRECT ANSWERS Discharge from contaminated groundwater
The Notice of termination can filed when: - CORRECT ANSWERS All construction
activity, inside and outside the building, is complete and permanent stabilization verified