to?
Stakeholder Unaware Resistant Neutral Supportive Leading
A C D
B C D
A Stakeholder B
B Stakeholder C
C Stakeholder D
D Stakeholder A
You are analyzing a document and notice that one of your stakeholders is unaware of the project, but you want
them to be supportive. What document are you most likely analyzing?
A Stakeholder engagement plan
B Power and interest grid
C Salience model
D Stakeholder engagement assessment matrix
When should you identify stakeholders on a project?
A At the beginning of the project
B While developing the project charter
C D Throughout
the project
D At the beginning of each phase of the project
, Who would least likely be considered a stakeholder in the following situations?
The vendor that you have decided to order raw materials from this one time and that you have never
done business with before
—
B A technical expert whom you sometimes refer to for advice
C End users of a system’s implementation project
D A building inspector who has to approve the work before the owners are allowed to move in
Which is the best way to meet stakeholders’ expectations?
A Hold weekly status meetings.
B Hold daily status meetings.
C Host team building sessions with stakeholders.
D Keep stakeholders regularly informed throughout the project.
You are determining your stakeholders’ current engagement levels compared to where you want them to be. Which
of the following would help you determine these levels?
A Resource calendar
B Stakeholder register
C Stakeholder management plan
D Stakeholder engagement assessment matrix
Which of the following tools might you use to identify stakeholders throughout your project? (Choose three.)
A Questionnaires and surveys
B Check sheet
C Meetings
D Statistical sampling
E Expert judgment