A Risk management plan
B Schedule baseline
C D Requirements documentation
D Resource management plan
E D Risk register
You are managing a project using a new approach for your organization. There are three distinct phases that are divided into several short iterations, and each
iteration will deliver a valuable product to the organization. What are these products best described as?
A Minimum viable product
B Requirements
C D Minimum business increment
D Deliverables
Who should the project manager interact with when performing integration processes?
A Key decision makers on the project
‘B D Any stakeholder
C The sponsor
D Team members
Explanation
Your team lead has approached you with an issue that you think might be a quick and easy fix. However, this was not in the original scope of the project. What
should you, as project manager, do next?
A Inform the sponsor.
B Tell the team lead to go ahead and fix the issue because it's a quick and easy fix.
C D Perform an impact analysis.
D Document and submit the change request to the change control board.
You are an experienced team facilitator recently hired by your company to lead its first agile project. Your team members are asking which artifacts they will need to
update as the project progresses. Which of the following is not an artifact used in Agile?
A Product backlog
B Sprint backlog
C Burndown chart
D D Schedule baseline