‘A D The development approach(es) selected will determine when and how frequently additional detail planning will occur.
B The development approach selection and the project life cycle determination are done before any project planning.
‘C D The development approach selection and the project life cycle determination are key aspects of project planning.
D After the initial planning is done, the development approach can be determined.
Which list best describes an agile development approach?
A Sprints, Scrum master, product owner, focus on maximum product value
Incremental and iterative development, strong project manager, minimal business involvement needed
@
C Iterations of two to four weeks, tight partnership between business and development, schedule is highest priority
D D Collaboration, expects change, deliver working product frequently, self-organizing teams
Which option contains valid deliverable variables that should be considered when selecting a development approach?
A Risk, delivery options, organizational structure
B D Requirements certainty, ease of change, safety and regulatory requirements
C Expected duration of the product life cycle, requirements certainty, ease of change
D Degree of innovation involved, scope stability, expected ROI
Which of the following descriptions would be considered examples of a hybrid development approach? (Choose two.)
A Requirements, Design, Development, Testing, Deploy
B Define Product Vision, Sprint 1, Sprint 2, Sprint 3, Sprint N
C j Requirements, Design 1, Develop 1, Test 1, Deploy 1, Design 2, Develop 2, Test 2, Deploy 2
D j Requirements, Sprint 1, Sprint 2, Sprint N, User Acceptance Testing, Deploy
Which development approach should be used if the project is determined to be a high-risk project?
A Adaptive/agile approaches are always the best option for high-risk projects due to their focus on generating a working product as soon as possible to
help manage uncertainty.
B It depends on the nature of the risks involved.
Hybrid development approaches are the best option for high-risk projects due to their use of the best aspects of predictive, incremental, and iterative
approaches.
D Predictive development approaches are the best option for projects due to the importance placed on detailed planning up front.