have a clear understanding of the scope of work - answers✔✔Before developing a project plan,
it is important to (CH3)
Both in-scope and out-of-scope items - answers✔✔A scope statement should include: (CH3)
the client's need - answers✔✔The key elements of a project should be driven by: (CH3)
A task that cannot begin before another task has been completed - answers✔✔What is a
dependency within a project task schedule? (CH3)
The amount of labor and materials the project manager has allocated to complete the project. -
answers✔✔Project budget refers to what? (CH3)
Identify changes to the original design that will affect the av installation. - answers✔✔A primary
reason for attending construction meetings is to: (CH3)
RFI - answers✔✔In the event of a change in the placement of air-conditioning ducts in a
boardroom, which of the following documents should the AV integrator submit first? (CH3)
RFC - answers✔✔Which of the following documents should an AV integrator submit in the
event that a manufacturer has discontinued a projector model? (CH3)
, project communication that needs to take place on a given project. - answers✔✔The
ANSI/INFOCOMM 2M-2010 Standard Guide for AV Systems Design and Coordination Process
lays out a procedure for determining the_________ (CH3)
System closeout activities are completed - answers✔✔After which of the following activities is
an AV project completed? (CH3)
Mechanical Drawings - answers✔✔Which set of drawings should you reference to view the
ductwork that goes through the building?
Electrical Drawings - answers✔✔Which set of drawings should you reference to locate a power
outlet for a video display?
Details of the system as finally installed - answers✔✔Which of the following must the as-built
drawings show?
Owner Furnished Owner Installed (you will not need to install) - answers✔✔OFOI
Related elevation drawings - answers✔✔What does an elevation flag on a plan drawing
indicate?
Detail Drawing - answers✔✔What type of drawing would you use to find out exactly how the
projector should be mounted to the ceiling?
• Install sprinkler system
• Run cables and install mounts - Answer
• Mount drop ceiling
• Build the firewall - answers✔✔Which of the following is the AV team likely to perform during
new construction?