1. Buying out the job is all about the
False
money and negotiating the best
price for the job.
Project Manager
2. The Construction Finance
Management Association say that
this person buy out the job most of
the time. False
3. According to our textbook, when we
are buying out the job, we can
assume that the drawings and
specifications are more or less
perfect, otherwise how can we buy Clauses that need to be passed on
out the job. the the sub-contrators.
4. According to our textbook, when
buy- ing out the project, the
project manager
should always review a contract for
these.
5. One way to make sure you do not miss any True
items when interviewing a sub-
contractor is to use a checklist or
interview form.
6. The textbook suggests that a can often be
project manager might want to contentious on a job
get these from sub-contractors as site, causing
they may help with change orders disagreements
later in the project. between the general
con- tractor and sub-
7. According to our textbook, this issue
1/
11
, CM 489 FINAL EXAM WITH ALL CORRECT & 100%
VERIFIED ANSWERS|LATEST VERSION|UPDATED TO
PASS
contractors. Unit Prices
Job Cleaning
8. Lien Waiver
2/
11
VERIFIED ANSWERS|LATEST VERSION|UPDATED TO
PASS
1. Buying out the job is all about the
False
money and negotiating the best
price for the job.
Project Manager
2. The Construction Finance
Management Association say that
this person buy out the job most of
the time. False
3. According to our textbook, when we
are buying out the job, we can
assume that the drawings and
specifications are more or less
perfect, otherwise how can we buy Clauses that need to be passed on
out the job. the the sub-contrators.
4. According to our textbook, when
buy- ing out the project, the
project manager
should always review a contract for
these.
5. One way to make sure you do not miss any True
items when interviewing a sub-
contractor is to use a checklist or
interview form.
6. The textbook suggests that a can often be
project manager might want to contentious on a job
get these from sub-contractors as site, causing
they may help with change orders disagreements
later in the project. between the general
con- tractor and sub-
7. According to our textbook, this issue
1/
11
, CM 489 FINAL EXAM WITH ALL CORRECT & 100%
VERIFIED ANSWERS|LATEST VERSION|UPDATED TO
PASS
contractors. Unit Prices
Job Cleaning
8. Lien Waiver
2/