During which of the following process, question such as what activities should be scheduled are
typically asked and answered?
- Planning
- Scheduling
- Control ✔Correct answer-Planning
Using traditional bar charts, it is always easy to tell the logic relationships between activities. (T/F)
✔Correct answer-False
An event consumes
- resources
- time
- both
- neither ✔Correct answer-Neither resources nor time
Which of the following is correct regarding Cpm and PERT?
- the calculations in CPM are non-deterministic and those in PERT are deterministic
- the calculations in CPM are deterministic and those in PERT are non-deterministic
- the calculations in both are deterministic
- the calculations in both are non-deterministic ✔Correct answer-the calculations in CPM are
deterministic and those in PERT are non-deterministic
Assume A is a milestone of a project, which of the following statement(s) can be true?
- A may take 3 days
- A needs one mason and two helpers to finish
- A costs $2,000
- A can at least be crashed by 1 day
- None of the above ✔Correct answer-None of the above
Which of the following statement is a correct description about the diagram? (Fig 1)
- The relationship between A and B is a start A and B is a start-to-finish relationship with zero days as
lag
- Five days after A is started, B can finish
- The relationship is a typical finish-to-start relationship with five days of lag
- Five days after A finished, B would start ✔Correct answer-Five days after A is started, B can finish
An activity's scheduled early start time is at the beginning of day 10. Its duration is 5 days. Its total
float is 7 days. If the activity is actually finished at the end of day 21, then which of the following
statement(s) must be true?
- The project will be delayed because of this activity
- The status of this activity will not cause a possible delay to the entire project
- The early start time of the successors of this activity will be delayed
- None ✔Correct answer-The status of this activity will not cause a possible delay to the entire
project
VERIFIED ANSWERS|ALREADY GRADED A+
During which of the following process, question such as what activities should be scheduled are
typically asked and answered?
- Planning
- Scheduling
- Control ✔Correct answer-Planning
Using traditional bar charts, it is always easy to tell the logic relationships between activities. (T/F)
✔Correct answer-False
An event consumes
- resources
- time
- both
- neither ✔Correct answer-Neither resources nor time
Which of the following is correct regarding Cpm and PERT?
- the calculations in CPM are non-deterministic and those in PERT are deterministic
- the calculations in CPM are deterministic and those in PERT are non-deterministic
- the calculations in both are deterministic
- the calculations in both are non-deterministic ✔Correct answer-the calculations in CPM are
deterministic and those in PERT are non-deterministic
Assume A is a milestone of a project, which of the following statement(s) can be true?
- A may take 3 days
- A needs one mason and two helpers to finish
- A costs $2,000
- A can at least be crashed by 1 day
- None of the above ✔Correct answer-None of the above
Which of the following statement is a correct description about the diagram? (Fig 1)
- The relationship between A and B is a start A and B is a start-to-finish relationship with zero days as
lag
- Five days after A is started, B can finish
- The relationship is a typical finish-to-start relationship with five days of lag
- Five days after A finished, B would start ✔Correct answer-Five days after A is started, B can finish
An activity's scheduled early start time is at the beginning of day 10. Its duration is 5 days. Its total
float is 7 days. If the activity is actually finished at the end of day 21, then which of the following
statement(s) must be true?
- The project will be delayed because of this activity
- The status of this activity will not cause a possible delay to the entire project
- The early start time of the successors of this activity will be delayed
- None ✔Correct answer-The status of this activity will not cause a possible delay to the entire
project