Should |the |construction |start |date |or |end |date |change, |what |is |required |to |be |submitted |to |
SMARTS? |- |correct |answersa. |A |revised |Notice |of |Intent |through |a |Change |of |Information.
b. |A |revised |risk |determination.
c. |An |amended |SWPPP.
d. |All |of |the |above. |(Correct |Answer)
Who |must |sign |the |No |Discharge |Technical |Report? |- |correct |answersa. |A |California |licensed |
professional |engineer |with |hydrological |expertise.
c. |A |California |licensed |professional |geologist |with |hydrological |expertise.
d. |a |or |c |(Correct |Answer)
Which |of |the |following |must |be |included |in |the |Notice |of |Termination |photo |documentation? |-
|correct |answersa. |A |description |of |the |corresponding |location |and |orientation |of |the |photos |
as |indicated |in |the |site |map.
b. |Photos |of |the |site's |final |site |conditions |and |post-construction |BMPs.
c. |a |and |b. |(Correct |Answer)
A |Notice |of |Termination |is |automatically |approved |if |no |action |is |taken |by |the |RWQCB |after |
what |amount |of |time? |- |correct |answers30 |days
Under |what |conditions |are |projects |exempt |from |the |post-construction |requirements |in |Order,
|Section |IV.N.3? |- |correct |answersa. |They |are |subject |to |the |post-construction |standards |of |an |
active |phase |I |MS4 |permit.
b. |They |are |subject |to |the |post-construction |standards |of |an |active |phase |II |MS4 |permit.
c. |They |are |linear |underground |and |overhead |projects.
d. |Any |of |the |above. |(Correct |Answer)
, Which |of |the |following |post-construction |stormwater |control |measures |require |Regional |Water
|Board |staff |review |and |approval? |- |correct |answersa. |Non-structural |measures.
b. |Structural |measures.
c. |a |and |b.
d. |Neither |a |nor |b. |(Correct |Answer)
Which |of |the |following |projects |might |apply |for |Programmatic |Permitting |Regulatory |
Coverage? |- |correct |answersRelocating |fiberoptic |cable |underground |while |repairing |
noncontiguous |sections |of |road |within |the |city |limits.
What |does |a |LUP |discharger |with |programmatic |permitting |coverage |submit |prior |to |
construction |activity? |- |correct |answersa. |A |SWPPP |covering |activities |common |to |all |the |
projects.
b. |A |linear |construction |activity |notification |describing |site-specific |project |name, |location, |
contact, |and |site |acreage.
c. |A |site-specific |map |detailing |pollutant |sources, |BMPs |implemented, |start |and |end |dates, |
and |risk |type.
d. |All |of |the |above. |(Correct |Answer)
Which |of |the |following |is |required |for |dischargers |removing |residential |lots, |within |a |larger |
common |plan |of |development |for |residential |use, |from |permit |coverage? |- |correct |answersa. |
The |residential |lot |is |one |or |more |acres.
b. |The |residential |lot |being |removed |is |currently |owned |by |the |developer |and |does |not |have |
occupants.
c. |The |unfinished |yard |and |landscaping |areas |are |free |of |construction |equipment |and |
temporary |BMPs.
d. |None |of |the |above. |(Correct |Answer)