CON 3910 FAC-C EXAM PREP COURSE EXAM QUESTIONS AND ANSWERS The contracting process consists of three Contract Life Cycle Phases: - CORRECT ANSWERPre-award, Award, and Post-award Which Cntract Life Cycle phase involves all the work performed by both the buyer (Government or prime contractor) and seller (contractor or subcontractor) in communicating the buyer's requirements and providing a solution to those requirements. - CORRECT ANSWERPre-award

Content preview

CON 3910 FAC-C EXAM PREP COURSE EXAM QUESTIONS AND
ANSWERS
The contracting process consists of three Contract Life Cycle Phases: - CORRECT ANSWER✅✅Pre-award,
Award, and Post-award



Which Cntract Life Cycle phase involves all the work performed by both the buyer (Government or prime
contractor) and seller (contractor or subcontractor) in communicating the buyer's requirements and
providing a solution to those requirements. - CORRECT ANSWER✅✅Pre-award



The pre-award phase consists of two primary activities: - CORRECT ANSWER✅✅Develop solicitation,
Develop Offer



What part of the FAR coves closeout of government contracts? - CORRECT ANSWER✅✅FAR Part 4.8



Who develops a solicitation? - CORRECT ANSWER✅✅The government and the buyer



Who prepares an offer? - CORRECT ANSWER✅✅The contractor and the seller



During the post-award phase while the contract is being performed, who has responsibility for quality? -
CORRECT ANSWER✅✅The Seller



Acquisition Team consists of: - CORRECT ANSWER✅✅govt representatives of technical, supply and
procurement

customers

contractors who provide product/service



Contracting Officer (KO) role on Acq team: - CORRECT ANSWER✅✅to determine the application of
rules, regulations, and policies, on a specific contract.



Contracting Officer (KO) General Responsibilities: - CORRECT ANSWER✅✅ensuring performance of all
necessary actions for effective contracting

,ensuring compliance with the terms of the contract

safeguarding the interests of the United States in its contractual relationships



Contractor Officer specific responsibilities: - CORRECT ANSWER✅✅Ensure Sufficient Funds

Dealing with Contractors

Request Assistance, as Appropriate (e.g. legal)

Designate COR



personal conflict of interest: - CORRECT ANSWER✅✅a contractor employee has some interest that
could impair their ability to act impartially and in the best interest of the Government when performing
under a contract



organizational and consultant conflicts of interest - CORRECT ANSWER✅✅contractor (or potential
contractor) is in a situation which by way of contract performance gives them an unfair advantage or will
bias their performance in making recommendations to the Government.



What part of the FAR is personal Conflict of Interest covered? - CORRECT ANSWER✅✅FAR Part 3



What part of the FAR is organizational Conflict of Interest covered? - CORRECT ANSWER✅✅FAR Part 9
Contractor Qualifications



contracting system must focus on "risk ________" rather than "risk ________." - CORRECT
ANSWER✅✅contracting system must focus on "risk management" rather than "risk avoidance." (FAR
Part 1)



T or F All contractors and prospective contractors should be treated the same. - CORRECT
ANSWER✅✅F All contractors and prospective contractors should be treated fairly and impartially but
need not be treated the same.



What part of the FAR stresses the importance of transparency to maintain the integrity of the
procurement process? - CORRECT ANSWER✅✅FAR Part 1

, Openness for the contracting officer applies primarily to? (Select all that apply) A) Acq Team B)
Contractors C) Offerors D) Contracting Team - CORRECT ANSWER✅✅All of the above



FAR 1.102-2(a) tells contracting professionals that a guiding principle of the Federal Acquisition System
is to satisfy customers in terms of what 3 things? - CORRECT ANSWER✅✅cost, quality, and timeliness of
the delivered product or service



What part of the FAR coves establishing, maintaining, and disposing of Government contract files? -
CORRECT ANSWER✅✅FAR Part 4



What 3 things does a KO have to meet to provide other than full and open competition? - CORRECT
ANSWER✅✅Justify in writing; certify accuracy/completeness of justification; obtain approval in FAR
6.3.



You need to document a business decision, such as the use of a specific contract type. What document
will you create? - CORRECT ANSWER✅✅Determination and Findings



When is a Determination and Finding used? - CORRECT ANSWER✅✅When it's required by statute or
regulation as a prerequisite to taking certain contract actions.



When is a Justification and Approval used? - CORRECT ANSWER✅✅To award a contract with other than
full and open competition.



At the conclusion of negotiations, the contracting officer will complete a: - CORRECT ANSWER✅✅Price
Negotiation Memorandum



SF-26 - CORRECT ANSWER✅✅Award negotiated contracts needing signature of both parties



SF-30 - CORRECT ANSWER✅✅Amendment to solicitation or modification of contract



SF-33 - CORRECT ANSWER✅✅Award negotiated contracts or sealed bidding contracts
(Solicitation/Offer and Award)

Document information

Uploaded on
August 8, 2025
Number of pages
27
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$12.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
STANGRADES
3.4
(14)
Sold
92
Followers
1
Items
12009
Last sold
2 weeks ago


Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions