Which of the following responses most accurately depicts the correct sequence of activities in the strategic planning process? A) strategic objectives - strategic analysis - guiding principles - flow-down objectives B) guiding principles - strategic analysis - strategic objectives - flow-down objectives C) strategic analysis - guiding principles - strategic objectives - flow-down objectives D) guiding principles - strategic objectives - flow-down objectives - strategic analysis - Answer -C) strategic analysis - guiding principles - strategic objectives - flow-down objectives Many writers have stated that effective objectives should be: A) broad - to cover many dimensions of the business B) measurable - to track progress C) unachievable - to inspire maximum performance D) resource based - to focus on the inputs - Answer -B) measurable - to track progress Managers performing project portfolio alignment will do all of the following EXCEPT: A) ensure that projects are planned and managed well B) identify and select projects to achieve strategic goals. C) prioritize a portfolio of projects and other work. D) assess the organization's ability to perform projects. - Answer -A) ensure that projects are planned and managed well Achieving project success is determined by all of the following EXCEPT: A) creating deliverables that include all required features B) involving only important key stakeholders C) completing the project on schedule and on budget D) providing outputs that please the project's customers - Answer -B) involving only important key stakeholders Projects are considered successful for all of the reasons below EXCEPT: A) members of the team learn new skills working on the project. B) the organization captures lessons learned for future projects. C) the team has demonstrated heroics to meet project objectives D) the organization reaps business level benefits. - Answer -C) the team has demonstrated heroics to meet project objectives 7. Which of the following actions will likely cause a project to fail? A) dedicating valuable team member time to identify risk events B) spending project funding to procure needed tools and spare parts C) failing to adequately plan the project D) conducting a project audit to evaluate performance - Answer -C) failing to adequately plan the project

Content preview

SCMA 350 EXAM 1 QUESTIONS & ANSWERS

Projects often require tradeoffs among all of the following EXCEPT:
A)Scope
B)Cost
C)Schedule
D)Programs - Answer -D) Programs

Once projects are completed, they will typically yield all of the following results
EXCEPT:
A) A unique product, service or result
B) Make or buy decisions
C) Stakeholders who interests are affected by the outcome.
D) A primary deliverable along with supporting deliverable - Answer -b) Make or buy
decisions

Project management involves the development of project plans that:
A) should never change once the project begins.
B) are frequently discarded once the actual work begins.
C) become more specific as early work is completed.
D) become less clear as the project progresses - Answer -c) become more specific as
early work is completed

Scope management typically involves which of the following processes?
A) acquiring, developing and managing the project team
B) ensuring that the project includes all the work required and only the work required, to
complete the project successfully
C) collecting, disseminating and storing appropriate project information
D) identifying, analyzing and controlling project risks - Answer -b) ensuring that the
project includes all the work required and only the work required, to complete that
project successfully

Typically, the senior customer representative is responsible for which of the following
project roles?
A) develops the project schedule and budget
B) determines how the project work will be accomplished
C) ensures the needs of the customer's organization are identified and prioritized
D) helps the project manager with running meetings and providing status report -
Answer -C) ensures the needs of the customer's organization are identified and
prioritized

Which of the following statements concerning strategic analysis is true?
A) Strategic analysis focuses exclusively upon external analysis.
B) External analysis focuses on the strengths and weaknesses of the organization.
C) Internal analysis focuses on the threats and opportunities facing the organization.

, D) External analysis focuses on the threats and opportunities facing the organization. -
Answer -D) External analysis focuses on the threats and opportunities facing the
organization

Which of the following responses most accurately depicts the correct sequence of
activities in the strategic planning process?
A) strategic objectives - strategic analysis - guiding principles - flow-down objectives
B) guiding principles - strategic analysis - strategic objectives - flow-down objectives
C) strategic analysis - guiding principles - strategic objectives - flow-down objectives
D) guiding principles - strategic objectives - flow-down objectives - strategic analysis -
Answer -C) strategic analysis - guiding principles - strategic objectives - flow-down
objectives

Many writers have stated that effective objectives should be:
A) broad - to cover many dimensions of the business
B) measurable - to track progress
C) unachievable - to inspire maximum performance
D) resource based - to focus on the inputs - Answer -B) measurable - to track progress

Managers performing project portfolio alignment will do all of the following EXCEPT:
A) ensure that projects are planned and managed well
B) identify and select projects to achieve strategic goals.
C) prioritize a portfolio of projects and other work.
D) assess the organization's ability to perform projects. - Answer -A) ensure that
projects are planned and managed well

Achieving project success is determined by all of the following EXCEPT:
A) creating deliverables that include all required features
B) involving only important key stakeholders
C) completing the project on schedule and on budget
D) providing outputs that please the project's customers - Answer -B) involving only
important key stakeholders

Projects are considered successful for all of the reasons below EXCEPT:
A) members of the team learn new skills working on the project.
B) the organization captures lessons learned for future projects.
C) the team has demonstrated heroics to meet project objectives
D) the organization reaps business level benefits. - Answer -C) the team has
demonstrated heroics to meet project objectives

7. Which of the following actions will likely cause a project to fail?
A) dedicating valuable team member time to identify risk events
B) spending project funding to procure needed tools and spare parts
C) failing to adequately plan the project
D) conducting a project audit to evaluate performance - Answer -C) failing to
adequately plan the project

Document information

Uploaded on
August 4, 2025
Number of pages
8
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$13.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
GEEKA
3.8
(361)
Sold
2134
Followers
1447
Items
58437
Last sold
5 hours ago


Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions